  1. ALSET YXES

    Anyone with a lower RN# than me?

    Got you beat may more than a 1000 units not that Tesla in is actually honoring the reservation numbers.
  2. ALSET YXES

    Supercharger - Bothell, WA

    So close I bet y'all can almost taste it... Bollards are in place around the cabinets but not secured. Should be soon for y'all... haha...
  3. ALSET YXES

    Supercharger - Bothell, WA

    May be sized for 12 but stupid regardless, just poor internal management by Tesla SC team.
  4. ALSET YXES

    Supercharger - Bothell, WA

    HM is finishing up final electrical terminations and WA L&I Electric final will take place shortly. Followed by Tesla Supercharger Service team commissioning the site. Reached out to a contact to see about commissioning ETA but no reply just yet. I’d say within the next 7 days dependent on...
  5. ALSET YXES

    Supercharger - Bothell, WA

    Supercharger Cabinets Set, New Transformer set, and still moving a snails pace.
  6. ALSET YXES

    277 vac Support. Does anybody have experience with it? Tesla can't help me.

    Yeah touché, but 99% of owners are installing a Nema 14-50s on a 50A breakers so @ 80% that's 40A max. as a $500 extension cord is a little excessive. :D
  7. ALSET YXES

    277 vac Support. Does anybody have experience with it? Tesla can't help me.

    @MXLRplus 277/480V is Level 3 Charging. Earlier and current Tesla wall charge posts support up to 240V 3ph. The differences between V2 & V3 wall charge posts is connectivity and that they no longer provide amperage over 40A as Tesla no longer provides dual on-board chargers in any of...
  8. ALSET YXES

    Gen 3 HPWC 208v Commercial Install Question

    At work? Does not seem like the work HPWC was programed correctly or it may be a Gen 2. https://www.tesla.com/sites/default/files/support/charging/Gen3_WallConnector_Installation_Manual.pdf
  9. ALSET YXES

    Gen 3 HPWC 208v Commercial Install Question

    There are din switches inside the HPWC that control the maximum output.
  10. ALSET YXES

    Supercharger - Forks, WA

    @Mattzilla Next time you're there can you get a straight on picture of the transformer/lightpole/charge post from a distance and up close? Cheers Mate!
  11. ALSET YXES

    Supercharger - Forks, WA

    Washington State Government is closed until further notice which includes WA L&I who will be performing the final inspection.
  12. ALSET YXES

    Sleeping at a supercharger?

    Sounds like a bit of a trip. The Superchargers are probably the safest place as they are generally in use at all hours. Always carry protection on a long road trip. Cheers!
  13. ALSET YXES

    Supercharger - Bothell, WA

    Not going to bite on that one Mr. @PLUS EV but a good project manger would have this done months ago. To satisfy everyone's insatiable need on here to have a completely unnecessary supercharger in Bothell Washington see below. New upgraded PSE transformer will be installed and March 24, 2020...
  14. ALSET YXES

    Supercharger - Bothell, WA

    Look at that *sugar* show... lol... I didn’t even post the picture I took of them setting everything the other day cause it looks so ugly. As this did not go through a official plan review the city may make them screen all that crap. PSE is upgrading the transformer to a larger 120/208V...
  15. ALSET YXES

    Supercharger - Bothell, WA

    ***Update*** Charge Posts wired up, massive step-up transformer on-site and about 6 pallets of additional materials arrived as well.
  16. ALSET YXES

    Supercharger - Bothell, WA

    ***Update*** Charge posts going in today, conductors pulled from Supercharger bases to posts. No step-up transformer on-site and switchgear still not installed.
  17. ALSET YXES

    Supercharger - Forks, WA

    Not surprised... #239
  18. ALSET YXES

    Supercharger - Forks, WA

    Not surprised...
  19. ALSET YXES

    Supercharger - Bothell, WA

    @Legacystar Don't lie you dig my passion!
  20. ALSET YXES

    Supercharger - Bothell, WA

    Based on actuals yes 3-6 months but can be much much faster with an experienced team in place.
  21. ALSET YXES

    Supercharger - Bothell, WA

    Nah, @Bwett is just trolling me... Cheers Mate!
  22. ALSET YXES

    Supercharger - Bothell, WA

    Not really... they have the conduit drop and pull cords for wire. They are layout mounting points for the charge posts. H&M was thinking ETA end of March but they are solely dependent on PSE to come through with a larger 120/208V transformer. In addition, it does not appear that their step...
  23. ALSET YXES

    Supercharger - Forks, WA

    @Mattzilla Are you swinging through anytime soon?
  24. ALSET YXES

    Supercharger - Kelso, WA

    Close, but no utility transformer on site and switchgear still needs to be set. ETA 4-6 weeks depending on local utility company.
  25. ALSET YXES

    Supercharger - Forks, WA

    hahahahaha... Any update here?
  26. ALSET YXES

    Charge Point chargers

    Charge Point maintains them and so requires them to be posted on their app/website. Just a bad business model for the end user.
  27. ALSET YXES

    How Many People Have Free Supercharging That Should Not

    Tesla is revolving door of employees so things get dropped, not updated or fall through the cracks. This is where my statement of incompetence on their part comes in to play. All about the mission and EM’s passion for our future but middle management on Tesla’s Supercharger Team is a real...
  28. ALSET YXES

    How Many People Have Free Supercharging That Should Not

    Incompetence at Tesla. I second “why do you care?” unless you’re a Tesla employee trolling the forums.
  29. ALSET YXES

    Supercharger - Forks, WA

    We'll see what Clallam County PUD does I can't imagine they'll energize the site with the light pole foundation within the 10 foot clearance area. Anyone passing through this week?
  30. ALSET YXES

    Supercharger - Bothell, WA

    Awww shucks man... Not putting words in anyones mouth just speaking from the my deep experience of making sh$t happen as it should. Perfection please that sh$t doesn't exist clearly... Only speaking to their clear incompetence as it directly pertains to execution of projects. If you are having...
  31. ALSET YXES

    Supercharger - Bothell, WA

    What can I say they are all about the mission! ;)
  32. ALSET YXES

    Supercharger - Bothell, WA

    ***Updates*** Supercharger Cabinets onsite, conduit runs progressing, concrete pad for switchgear and new transformer still not poured.
  33. ALSET YXES

    Supercharger - Forks, WA

    Pizza joint is the spot...
  34. ALSET YXES

    Supercharger - Bothell, WA

    Not my window... haha...
  35. ALSET YXES

    Supercharger - Forks, WA

    *** I RETRACT THIS STATEMENT *** "If it's nice this week commissioning and stripping and she should be hot." Due to MASSIVE F*&K UP by Tesla/GC see edit photo below. No way Clallam County PUD will run conducters without 10 foot clear in front of the transformer. Original design had the charge...
  36. ALSET YXES

    Supercharger - Forks, WA

    Much better shot. The 2 pallets there look to be 2 V3 supercharger cabinets one more thing to check off.
  37. ALSET YXES

    Supercharger - Bothell, WA

    As you very well should haha... :rolleyes:
  38. ALSET YXES

    Supercharger - Bothell, WA

    Switchgear has arrived!
  39. ALSET YXES

    Supercharger - Bothell, WA

    ...and you wouldn't be to far off point but H&M Electric has been on-site since early November so well over 37 days.
  40. ALSET YXES

    Supercharger - Bothell, WA

    Building stuff is black & white if you're doing it right. It's easy to assume something is complicated if you've never actually done it. I love all the #fanboys on here. Cheers! oh and you're welcome... :rolleyes:
  41. ALSET YXES

    Supercharger - Bothell, WA

    haha... Goodish data about 90% accurate as 3rd party data usually is. Case in point Bothell has always been a 10 stall site since 2018 planning.
  42. ALSET YXES

    Supercharger - Bothell, WA

    haha... Watched the mismanagement of that one too... Though that was more the fact the The Washington Department of Ecology owns the property and everyone of the tenants had to sign off on the agreement with Tesla. Had to back charge the GC for repaving after they started construction without...
  43. ALSET YXES

    Supercharger - Forks, WA

    I get that... Your ignorance is bliss.
  44. ALSET YXES

    Supercharger - Bothell, WA

    Weather has zero to do with that is just a lazy persons excuse. Cle Elum was built in November 2018 in the snow with 12 Tesla stalls and 3 stalls from EV4 in just 23 days!!! That was a completely developed site ie a grass field to Tesla's and other EV's charging on day 23 so please tell me...
  45. ALSET YXES

    Supercharger - Bothell, WA

    ***Update*** Some conduit in the ground. No progress to speak of in the inside. One of the slowest builds outside of Blaine, WA and Forks, WA.
  46. ALSET YXES

    Supercharger - Forks, WA

    Don't hold your breath... But that would be cool to finally see this site operational.