The tesla lettering at the top of the pedestals arn't illuminated in the latest photos though it's hard to tell. I thought this was the main indication that they were live/working.
On the way back they were working on the transformer pad looks they had framing up the pour and had installed some conduit general contracting work was moving quickly
Dropped by the Monroe site. Looks to be ready for inspection, Meter, 3 pole mounted 144kva 277/480 transformers, 800 amp 3 phase disconnect. Meter reads zero. Pedestal covers are on but are missing the anti theft screws
Monroe Looks ready to go pole transformers meter and switchgear in place with 800 amp 3 phase disconnect however pedestals don't have anti theft screws installed probably for final inspection and meter was at zero