5 battery install Lake of the Pines

h2ofun

Active Member
Aug 11, 2020
1,232
192
auburn, ca
Here is a picture of the 5 30 amp battery disconnects. The two 60 amp inverter disconnects will be placed at the end of the PW's based on how the cable is running.
 

Attachments

  • disconnect.jpg
    disconnect.jpg
    399.6 KB · Views: 25

Electrph

Member
Aug 29, 2019
250
152
Central California
I will end up with 8 in the house, 5 batteries, 2 inverter and 1 generator. Crazy
ok so now i'm seeing you in a mad scientist lab coat at halloween flipping blade disconnects .. "it's alive!!"

seriously though the relative complexity of your system is intriguing .. can't wait for photos of all final components
 

Electrph

Member
Aug 29, 2019
250
152
Central California
Huh. Is it a CA thing to have a separate blade disconnects for each Powerwall? We have only one for our three Powerwalls here in MA.
the extent of them seem to be a county requirement in some areas .. the ridiculousness of some of them has become the butt of jokes on some threads
my specific CA county system completed Dec 2020 required only one giant blade disconnect outside for whole system (individual breakers inside garage in TEG were apparently adequate for each powerwall)
 
Last edited:

holeydonut

Supporting Member
Jun 27, 2020
873
518
East Bay NorCal
I wonder if they're going to mess with H2o and put the blade disconnects in a different order than his Powerwalls.


Like his PWs are going to go on the wall like this: [1] [2] [3] [4] [5]

But they could put his blade disconnects like
[5]
[4]
[3]
[1]
[2]

#stillbeatingthebladedisconnecthorsewhichdiedlongago
 
Last edited:

jjrandorin

Moderator, Model 3, Tesla Energy Forums
Nov 28, 2018
7,197
7,980
Riverside Co. CA
the extent of them seem to be a county requirement in some areas .. the ridiculousness of some of them has become the butt of jokes on some threads
my specific CA county system completed Dec 2020 required only one giant blade disconnect outside for whole system (individual breakers inside garage in TEG were apparently adequate for each powerwall)

Seems to be very county specific, at least right now here in CA. I also only have 1 blade disconnect, but I also only have 2 powerwalls. Perhaps the requirements change with 3 or more here? I dont know but may find out at some point as I might add another one at some point.
 

h2ofun

Active Member
Aug 11, 2020
1,232
192
auburn, ca
Seems to be very county specific, at least right now here in CA. I also only have 1 blade disconnect, but I also only have 2 powerwalls. Perhaps the requirements change with 3 or more here? I dont know but may find out at some point as I might add another one at some point.
In nevada county it is 1 for 1 disconnect. Same for inverters
 

h2ofun

Active Member
Aug 11, 2020
1,232
192
auburn, ca
Was just able to log into the first TEG I hard wired. Fun about to begin. Will see if they can finish today. They worked 11 hours tuesday, and 12 hours yesterday. Solar panel guys are here to put in new inverter and change things around. BUSY!!
 

h2ofun

Active Member
Aug 11, 2020
1,232
192
auburn, ca
Well, they are done for a first pass. Batteries working. Now need to learn how to use. See if anything is impacted.
 

Attachments

  • b7.jpg
    b7.jpg
    361 KB · Views: 17
  • b6.jpg
    b6.jpg
    339.1 KB · Views: 15
  • b5.jpg
    b5.jpg
    416.3 KB · Views: 14
  • b3.jpg
    b3.jpg
    428.6 KB · Views: 14
  • b2.jpg
    b2.jpg
    270.8 KB · Views: 13
  • b1.jpg
    b1.jpg
    273.4 KB · Views: 16

h2ofun

Active Member
Aug 11, 2020
1,232
192
auburn, ca
Not sure what all the next steps are to be done such that my SGIP rebate can be filed. What are other experiences? Clearly I need a final inspection from my county. But after that, no idea how SGIP or PGE are involved.
 

jjrandorin

Moderator, Model 3, Tesla Energy Forums
Nov 28, 2018
7,197
7,980
Riverside Co. CA
Not sure what all the next steps are to be done such that my SGIP rebate can be filed. What are other experiences? Clearly I need a final inspection from my county. But after that, no idea how SGIP or PGE are involved.

The poster here with the most experience with your scenario is @RKCRLR . You could try PM ing them and checking what their process with that specific situation was. Like you, they filed under equity and resiliency, and have been installed for a while so might have more feedback for you directly.
 

RKCRLR

Member
Apr 13, 2020
250
101
Garden Valley, CA
For me, Tesla did everything. The only thing I could do was try to push them.
You need PG&E PTO before you can file as I remember. And you need to be on a EV rate plan before they will authorize the incentive. It was never clear to me who was responsible for switching rate plans (I filled out a form authorizing Tesla to do it but nothing happened) so I changed the rate plan myself.
 

h2ofun

Active Member
Aug 11, 2020
1,232
192
auburn, ca
For me, Tesla did everything. The only thing I could do was try to push them.
You need PG&E PTO before you can file as I remember. And you need to be on a EV rate plan before they will authorize the incentive. It was never clear to me who was responsible for switching rate plans (I filled out a form authorizing Tesla to do it but nothing happened) so I changed the rate plan myself.
Interesting. I guess the next step is to get a county final approval.

My installer has been great about filing paperwork. Did anyone ever come out and do an inspection from PGE or SGIP?
So you had to change the rate plan? Why if no one did? And what form or person said you had to change before they would authorize incentive?
Details :(
 

h2ofun

Active Member
Aug 11, 2020
1,232
192
auburn, ca
I just kicked my batteries to self powered 20%. Will see if I can get off grid with my setup? I am going to looking into some more solar for my 3 battery heating system inverter, since clearly that is where my main usage is. And since the gateways seem to not to be able to share solar between them, if I want to try and just make the battery use simple, I need enough solar to try and charge them to greater than usage.

The performance tab on the app is great, since it shows me directly how my solar production compares to my usage. And my house side, I look good. Heating cooling side would need some more. Heck, one only lives once. If I am this close to getting off grid most of the time, might just go for it. :(
 

About Us

Formed in 2006, Tesla Motors Club (TMC) was the first independent online Tesla community. Today it remains the largest and most dynamic community of Tesla enthusiasts. Learn more.

Do you value your experience at TMC? Consider becoming a Supporting Member of Tesla Motors Club. As a thank you for your contribution, you'll get nearly no ads in the Community and Groups sections. Additional perks are available depending on the level of contribution. Please visit the Account Upgrades page for more details.


SUPPORT TMC
Top