Yet another thread.. BUT this one has a slight twist.
I let Tesla know that I would like to install EV charging. I already knew that they would not do the install themselves but I wanted them to add a 50A breaker to the load calculation to allow me to add it to the backup panel after solar install.
Here is the response I received today.
"I have included the plan set for your review.
Tesla does not installed EV charging or outlets that may be required. Once the breaker is added I can check to see if the EV breaker can be included in the backup loads.
Please keep in mind that the EV charger MUST be permitted."
I replied and said I dont have room to install the breaker now; subpanel is full (and far away).
Any thoughts? I thought proactively "letting them know" was the right thing to do.
I let Tesla know that I would like to install EV charging. I already knew that they would not do the install themselves but I wanted them to add a 50A breaker to the load calculation to allow me to add it to the backup panel after solar install.
Here is the response I received today.
"I have included the plan set for your review.
Tesla does not installed EV charging or outlets that may be required. Once the breaker is added I can check to see if the EV breaker can be included in the backup loads.
Please keep in mind that the EV charger MUST be permitted."
I replied and said I dont have room to install the breaker now; subpanel is full (and far away).
Any thoughts? I thought proactively "letting them know" was the right thing to do.