Construction Started at Warwick Services - M40(N)

Discussion in 'The UK and Ireland' started by WannabeOwner, Mar 14, 2017.

  1. WannabeOwner

    WannabeOwner Active Member

    Joined:
    Nov 2, 2015
    Messages:
    1,612
    Location:
    United Kingdom
    According to Supercharger Info: at Warwick Services on M40 J12-J13 - North-side (based on zooming-in on the map co-ordinates).

    4 stalls

    SC_Warwick.jpg
     
  2. DrBobM

    DrBobM Member

    Joined:
    Oct 27, 2016
    Messages:
    14
    Location:
    Swansea, UK
    I wonder how certain the 4 stalls bit is? My understanding from most discussion and from Georg Ell's clubhouse presentation at Bristol recently was that all new installations would be 8-12 stalls?
     
  3. WannabeOwner

    WannabeOwner Active Member

    Joined:
    Nov 2, 2015
    Messages:
    1,612
    Location:
    United Kingdom
    Yup, I just lifted that from Supercharger Info, and it did seem "awfully small" to me (I have no idea if the site is tight) ... FWIW the other ones that have been recently added to Supercharger Info have had varying Stall Numbers - so perhaps some real-world basis, but time will tell of course.
     
  4. mrkisskiss

    mrkisskiss Member

    Joined:
    Jan 26, 2017
    Messages:
    144
    Location:
    London
    How long does it take to install superchargers, roughly? Will it be online by April?
     
  5. arg

    arg Supporting Member

    Joined:
    Aug 22, 2012
    Messages:
    907
    Location:
    Cambridge, UK
    Highly variable. The actual construction work typically takes 2-3 weeks, but often there are other things that need to be done to actually make it work - getting the power connected to the site is often the one that causes unpredictable delays.

    So the ones that are well under way (Woodall, Newport Pagnell, maybe Warwick) will probably be built by the end of this month, but may or may not be turned on immediately. Sometimes it's the next day, sometimes it's weeks or even months later.
     
    • Like x 1
  6. WannabeOwner

    WannabeOwner Active Member

    Joined:
    Nov 2, 2015
    Messages:
    1,612
    Location:
    United Kingdom
    According to Supercharger Info: construction has now also started on Warwick South-side, 6 stalls.
     
  7. WannabeOwner

    WannabeOwner Active Member

    Joined:
    Nov 2, 2015
    Messages:
    1,612
    Location:
    United Kingdom
    Warwick NORTH now open - 8 stalls
     