Ten weeks after my install and inspection, and what I thought was PTO submission, I received a notice today from Tesla to sign an addtional "CPUC Solar Packet" document which sounds like it should have been signed at project onset and is required by SCE. Within hours, I received notices from both Tesla and SCE that my request for PTO has been submitted/received.
So after 10 weeks of wasted time my the PTO clock resets. Luckily this is for an additional solar capacity and 2 PW's so my original solar system's PTO is still in effect and I'm abile to supply excess capacity to the grid (albeit slightly capped at my original systems capacity).
Coincidentally, this happened just a day after I requested a PTO status update along with another question to Tesla. I believe the movement likely would not have happened if I had not inquired.