SCE / Los Angeles, installer was Semper Solaris. I added extra panels to my system, basically said "fill up the rest of the available roof area".
Design start 9/3
Install 12/8
Initial inspection 12/20
2nd inspection passed 1/10
PTO application 1/13
SCE PTO application received 1/13
SCE Deemed valid 1/20
SCE Technical review 2/1
SCE PTO 2/4
Design phase took longer than expected, as we went back and forth a lot because I now have more than 7.6KW of panels and only 1 power wall, which is outside of Tesla guidelines, they wanted to tie the extra panels in before the gateway, so they'd turn off during a power outage.
I only accepted the design when they put it with the rest of the solar, and with a waiver that the system could shut itself down during an outage due to too much solar and nowhere for it to go.