How much to install Level 2 charger at condo?

Discussion in 'Charging Standards and Infrastructure' started by ZeApelido, Oct 9, 2017.

  1. ZeApelido

    ZeApelido Member

    Joined:
    Jun 1, 2016
    Messages:
    71
    Location:
    The Peninsula, CA
    Ok I know this is too generic of a question, but any resources / advice are appreciated.

    I live in a condo, and informally asked the HOA about possibly installing a level 2 charger in a guest spot by the pool, so other condo owners could use it as well. This would require probably running a line underground about 50 ft or so to the parking spot. They claimed to have looked into it a few years ago getting a quote around $20,000. That seems egregious unless I am missing some specific information unique to this situation.

    About how much should it cost? Does anyone know of reputable companies I could contact to get a quote?

    Thanks!
     
  2. KJD

    KJD Supporting Member

    Joined:
    Dec 14, 2013
    Messages:
    803
    Location:
    SLC, UT
  3. kort677

    kort677 Active Member

    Joined:
    Sep 17, 2015
    Messages:
    4,574
    Location:
    florida.
    while $20k seems absurdly high I don't know the level of service the condo currently has, what type of digging/wall work needs to be done. if the service needs to be upgraded that could add to the cost significantly and lastly if permitting is necessary that could be costly. I would get other quotes and then build a presentation for your HOA. as for who to call, any competent electrician should be able to do this type of work.
     
  4. miimura

    miimura Active Member

    Joined:
    Aug 21, 2013
    Messages:
    2,045
    Location:
    Los Altos, CA
    In most HOA situations, if you want something done you need to get your own bids and present one or several solutions for approval. Asking for a solution is very unlikely to get any action.
     