1. Order placed on 9/16
2. Design for 10.4KW finalized on 9/26
3. Township approval on 9/27
4. Utility company approval on 10/21
5. Installation on 12/2
6. Township inspection on 12/7
7. Final CC payment on 12/8
10. Final paper submission by Tesla to utility for Certificate of Completion on 12/16
11. DER box installation by utility company on 12/28
12. PTO approval from utility company on 12/28
13. Pending Tesla Energy App and SolarEdge monitoring App still not working.
2. Design for 10.4KW finalized on 9/26
3. Township approval on 9/27