MountainHigh
Member
That Tesla blog was one of the funniest things I've read this year. I'd be happy if they managed to complete what they planned by end of 2016 this year.
You can install our site as a web app on your iOS device by utilizing the Add to Home Screen feature in Safari. Please see this thread for more details on this.
Note: This feature may not be available in some browsers.
There is one possibility that I have stated before that actually fits both no permits and the aggressive rollout working: they haven't been starting until now, and we see the mass of permits coming soon. It can all be done in under half a year. But, it would take about that much time to do in a currently efficient format using current normal methods (I'm not ruling out some new method to use, but I find that slightly unlikely).If there announced plan was anything close to reality, we'd already see a *MASSIVE* spike in permits and construction activity before now to even have a chance at opening that many new locations in the next 8 months.
That seems realistic. I think it may be bunched up a little more in the later months, a little, with thinner earlier months.Looking at @stopcrazypp numbers from his 'webfu', we are adding 346 sites in 2017. Now, I'm using my spreadsheet for a hypothetical ramp (disregard my earlier June-December numbers... sum doesn't add):
YTD 16
May 14
June 22
July 38
August 45
September 52
October 60
November 80
December 30
-----------
Total 357 (ish)
There is one possibility that I have stated before that actually fits both no permits and the aggressive rollout working: they haven't been starting until now, and we see the mass of permits coming soon. It can all be done in under half a year. But, it would take about that much time to do in a currently efficient format using current normal methods (I'm not ruling out some new method to use, but I find that slightly unlikely).
1-2 months design (starting April 24, 2017), starting with the long-lead-time targets first, so 2-3 weeks for Bay Area sites.Even if that happens how are they going to go from "permit application" (assuming in the next few weeks) to construction completed and open for business before the end of 2017 on 17 new Bay Area supercharger locations?
1-2 months design (starting April 24, 2017), starting with the long-lead-time targets first, so 2-3 weeks for Bay Area sites.
2-3 months permit process.
2-3 months construction, with tail end overlapping PG&E transformer timing extending another 3 weeks.
2-3 weeks testing after PG&E transformer installed.
Total max time: 7.61 months, putting it at January 19th (almost very worst case, worst case being those sites that never get approved "timely") open up time for the worst cases, and for the medium cases, December 3rd, well within 2017. Faster areas will be much sooner, and will probably be at least 40% of the turn ups, and we'll start to see them in process in a few months.
When doing a large number of any complex thing, many more will complete timely than if doing a smaller number. The spikes are reduced when you increase the number.
even your numbers could be seen as being overly optimistic.1-2 months design (starting April 24, 2017), starting with the long-lead-time targets first, so 2-3 weeks for Bay Area sites.
2-3 months permit process.
2-3 months construction, with tail end overlapping PG&E transformer timing extending another 3 weeks.
2-3 weeks testing after PG&E transformer installed.
Total max time: 7.61 months, putting it at January 19th (almost very worst case, worst case being those sites that never get approved "timely") open up time for the worst cases, and for the medium cases, December 3rd, well within 2017. Faster areas will be much sooner, and will probably be at least 40% of the turn ups, and we'll start to see them in process in a few months.
When doing a large number of any complex thing, many more will complete timely than if doing a smaller number. The spikes are reduced when you increase the number.
Because they have to pay for it, unlike almost every other Tesla to date. I wonder how much SuperCharger use diminished with the advent of pay-for-charge for S & X...
But the average time from permit application to being open for business for california superchargers is a lot longer than that.
Does it really matter if this happens by the end of 2017 or the end of 2018. I think not.
I will be glad to see the expansion happen, whenever it happens, this year or next year, its all good.
Average time to completion is around 183 days, isn't it? That's plenty of time to reach this year. Wasn't there a web site tracking that? I can't find it on SuperCharge.Info; did they remove it, or was it a different site?even your numbers could be seen as being overly optimistic.
site acquisition, obtaining the necessary building and zoning permits, and then bringing in the necessary power all take time. even the average amount of time will not be enough in the majority of locations.Average time to completion is around 183 days, isn't it? That's plenty of time to reach this year. Wasn't there a web site tracking that? I can't find it on SuperCharge.Info; did they remove it, or was it a different site?
If they are streamlining it and using economies of scale, it could knock weeks or even months off that number. On the other hand, if they aren't trying to streamline it and are just dumping a huge workload on a bunch of uninspired wrongly educated mismanaged office droids, I can see the crushing workload as being disastrous to timelines. All depends on proper management.
Double the number of cars and you double the number of supercharging sessions
site acquisition, obtaining the necessary building and zoning permits, and then bringing in the necessary power all take time. even the average amount of time will not be enough in the majority of locations.
maybe they did, but if they did they wouldn't have posted such vague locations on their map. the posting of such vague locations leads me to believe this is more of a wish list than it is an actual portrayal of where the units are going to be located.And they could have already done a lot of that with us never knowing...
maybe they did, but if they did they wouldn't have posted such vague locations on their map. the posting of such vague locations leads me to believe this is more of a wish list than it is an actual portrayal of where the units are going to be located.
almost every SpC location has been disclosed either by tesla or by the sleuths once permitting has begun. for example the locations in NYC are denoted by downtown, midtown, uptown, queens. these are huge areas and those notations show that this is no more than a wish listI don't think that is true, Tesla won't release/announce the actual location of a Supercharger until it is in operation, even after we have found the permit and have seen the construction started.
almost every SpC location has been disclosed either by tesla or by the sleuths once permitting has begun. for example the locations in NYC are denoted by downtown, midtown, uptown, queens. these are huge areas and those notations show that this is no more than a wish list