If you’re ever desperate for a charge and JFK is backed up, there are new 150 kW chargers at the nearby cell phone lot.
At least two of the stalls even come with Chademo adapters for Teslas.
I had a chance to stop by the Superchargers being installed at JFK yesterday and take a couple of pictures.
They are being installed at the new JFK Airport Travel Plaza JFK Travel Plaza at 150 Ave and 147th Street, Queens NY. I tried a few things to have the Tesla Nav system take me directly there, but I couldn't get the system to navigate to the exact correct place, especially because I wasn't sure exactly where it was! Once you know where it is, it's an easy on/off of the highway.
It looks like they have all the equipment there, and conduit run, but no cables are pulled yet, so it still has a ways to go... I'm told that the next step is an inspection on Monday.
Oh, the full location is under construction still, but is nearing completion. Along with gas, they will also have CNG fueling, a larger indoor eating area, free wifi, etc.
Peter
View attachment 36902View attachment 36904View attachment 36906View attachment 36905View attachment 36903View attachment 36908View attachment 36907
Tesla nav says closed. Anyone have any info?I haven't looked and will never use but that is the first public cng filler I've ever seen except at the aqmd office in diamond Barr California - then I haven't been East of the Mississippi since '74
It does look like they are putting in some more chargers. Here is a 811 Ticket from 2 weeks ago.I was there the other day. That entire area is fenced off, including the parking spots next to the SCs where Black Cars used to park. The cabinets and chargers themselves were disconnected and moved and put next to each other on the asphalt. Not sure what is happening. My first thought was perhaps they are going to put in more chargers and upgrade them. That are would easily fit 8-10 chargers.
I decided to swing by there today after I dropped somebody off at the airport. There was a lot of construction activity and I spoke to the Foreman. He said that there are going to be 12 V3 chargers and that they should be finished with their work by the end of next week. He said, however, that the long delays usually come from the utility companies. He couldn’t really guess when they would be operational.It does look like they are putting in some more chargers. Here is a 811 Ticket from 2 weeks ago.
@corywright @ChuqI was there the other day. That entire area is fenced off, including the parking spots next to the SCs where Black Cars used to park. The cabinets and chargers themselves were disconnected and moved and put next to each other on the asphalt. Not sure what is happening. My first thought was perhaps they are going to put in more chargers and upgrade them. That are would easily fit 8-10 chargers.
Perhaps this should be changed to a construction cone rather than a temporary closure since they’re installing 12 V3 chargers.@corywright @Chuq
Please change SC.info status to temporary closed until the rebuild is finished and activated.
I thought about that, but if we set it to "under construction" then it could be interpreted as "open, but expansion under construction" to people who already knew about the previous Superchargers there. Setting it to temporary offline makes it clear that no Superchargers are online there.Perhaps this should be changed to a construction cone rather than a temporary closure since they’re installing 12 V3 chargers.
I'd suggest keeping the current status, power and stall count as site level.I thought about that, but if we set it to "under construction" then it could be interpreted as "open, but expansion under construction" to people who already knew about the previous Superchargers there. Setting it to temporary offline makes it clear that no Superchargers are online there.
People rely on supercharge.info and the apps that use our API for trip planning, so I think we should be cautious in situations like this. Ultimately we'll need to add more statuses to the supercharge.info backend to support scenarios like these.
I checked out the site the other day, and I guess the Foreman I had spoken to was correct. The chargers are installed but they need to be hooked up and given final inspection. Nobody was there, although it was early (7am). The area is completely fenced off.I decided to swing by there today after I dropped somebody off at the airport. There was a lot of construction activity and I spoke to the Foreman. He said that there are going to be 12 V3 chargers and that they should be finished with their work by the end of next week. He said, however, that the long delays usually come from the utility companies. He couldn’t really guess when they would be operational.
I checked out the site the other day, and I guess the Foreman I had spoken to was correct. The chargers are installed but they need to be hooked up and given final inspection. Nobody was there, although it was early (7am). The area is completely fenced off.View attachment 737007View attachment 737008