May 17th notes from Signal Hill.
Tenant improvements for a new TESLA auto dealership and service center at former Nissan site
On 2/8/21, application and dev. deposit submitted.
On 2/10/21, applicant submitted narrative letter outlining the proposed uses at the site.
On 3/24/21, the Planning Department approved the plans and routed to Building for plan check review.
On 4/20/21, a conformity report was presented to the Planning Commisison.
On 7/7/21, plans approved by the building plan check firm (Interwest).
Building permit issued on 7/23/21.
Soils samples taken on 10/13/21.
On 12/13/21, Tesla submitted a request letter to extend the expiration date of the permit, which would expire on 1/19/22.
On 12/14/21, the Building Department approved a 90-day extension with a new expiration date of 4/19/21.
On 2/23/22, Building Inspector inspected underground sweeps from property line to transformer to new cabinet location behind wall. Ok'd to backfill.
On 4/6/22, Building Inspector conducted site visit with TI contractor to extend permit. No work performed inside yet.
On 4/11/22, applicant initiated TI construction.
Project is under construction. Contractor must call for Inspections.
Permit was extended and expires Jan 14th 2023.