Timeline
7/28 - Placed order for 8.16 kwh panels + 2 Powerwalls.
7/28 (after few hours) - First layout plan from Tesla. I approved asap.
7/29 - Request to send a bunch of photos from garage, panels etc.
7/30 - Sr Solar advisor (based in Las Vegas) assigned.
8/4 - Called advisor and asked if he can request engineer to move 6 panels from North to South / SouthEast.
8/6 - Got updated plan and approved it as they changed layout per my request.
8/7 - Got a call to setup an appointment for site survey. Appointment setup for 8/20 Monday between 11 - 1 pm.
8/8 - Status is HOME ASSESSMENT (with 8/10 date).
Next step is PERMIT. The solar advisor told me that the permit has already been applied on 7/30 so thats whats confusing me. He said layout changes don't need to be repermitted as size of panels are the same (8.16 kwh).
Is there a checklist for site survey that needs to be asked?
7/28 - Placed order for 8.16 kwh panels + 2 Powerwalls.
7/28 (after few hours) - First layout plan from Tesla. I approved asap.
7/29 - Request to send a bunch of photos from garage, panels etc.
7/30 - Sr Solar advisor (based in Las Vegas) assigned.
8/4 - Called advisor and asked if he can request engineer to move 6 panels from North to South / SouthEast.
8/6 - Got updated plan and approved it as they changed layout per my request.
8/7 - Got a call to setup an appointment for site survey. Appointment setup for 8/20 Monday between 11 - 1 pm.
8/8 - Status is HOME ASSESSMENT (with 8/10 date).
Next step is PERMIT. The solar advisor told me that the permit has already been applied on 7/30 so thats whats confusing me. He said layout changes don't need to be repermitted as size of panels are the same (8.16 kwh).
Is there a checklist for site survey that needs to be asked?