We have an open problem with Tesla's solar roof after two years of operation.
The contract says the following:
Site & Design Assumptions for your Purchase Solar Roof system size: 21.98472 kW DC Estimated gross annual electricity production in kilowatt-hours (kWh) from your Solar Roof in Year 1: 25,259 kWh
Production for each of the 2 years has been ~17,000 kwh, only about 2/3rds the number projected. They've offered to add some panels on the north side, but we don’t have any confidence that will change the overall production that much.
Is this something that should go to arbitration?
The contract says the following:
Site & Design Assumptions for your Purchase Solar Roof system size: 21.98472 kW DC Estimated gross annual electricity production in kilowatt-hours (kWh) from your Solar Roof in Year 1: 25,259 kWh
Production for each of the 2 years has been ~17,000 kwh, only about 2/3rds the number projected. They've offered to add some panels on the north side, but we don’t have any confidence that will change the overall production that much.