City of Goodland Electric did their part, to the meter ! Wanted: Contractors
Someone did their part getting the conduit from the power line to the transformer pad, either Goodland Electric or the contractor; at least there is no power line easement issue! When the contractor gets the Distribution Center in place, conduits from the transformer pad to the Distribution Center in, and the Transformer Pad poured, then Goodland Electric can set the transformer, pull the medium Voltage wires from the power line to the Transformer, pull the 480-Volt wires from the transformer to the Distribution Center, install the meter on the Distribution Center, and connect it all up.
I want to see another 3-week install!!!
Who knows if the Ritzville crew heads to Limon, and this crew gets going, maybe they will just leapfrog each other from Denver heading east! Limon, Goodland, Hays, Salina, Topeka, ... If they really can do 3-weeks per site, that would be very nice!