mhh

Member
Jul 24, 2014
333
53
Adelaide
I dropped by just now and the workers said that they were a week and a half from finishing. It looks closer being ready than that - maybe they were being cautious.
 

BenT

Member
Nov 16, 2015
375
187
Adelaide, SA, Australia
No photos today. Yesterday evening the red Tesla signs on the top of each of 4 chargers were illuminated indicating there was power running. Today the Tesla chargers are fully wrapped in black plastic so can't see if he lights are on. There is now one EVlink and 2 Veefil chargers installed at the southern end. All it needs now is minor landscaping and some white lines for the parking bays. Now I am getting impatient.
 
  • Informative
Reactions: bradjc and Chuq

mhh

Member
Jul 24, 2014
333
53
Adelaide
IMG_0072.JPG
IMG_0073.JPG
Just drove past Adelaide SC station. It's still fenced off. Furious landscaping is happening.
 

BenT

Member
Nov 16, 2015
375
187
Adelaide, SA, Australia
Too dark for decent photos but it is all scrubbed and cleaned up with plantings in and line markings and bold Tesla branding and EV markings on the asphalt to make it clear that this is an EV charging station. All ready for opening by the looks of it!
 

BenT

Member
Nov 16, 2015
375
187
Adelaide, SA, Australia
I am informed that there will be an official opening of the Adelaide Supercharger tomorrow at 1245 and any Tesla owners would be welcome to attend. There will be limited parking so you may have to wait until after the opening to charge.
 

srwx

"perf_config": "P1"
May 16, 2016
146
226
Ballarat, Australia
According to supercharge.info, the first evidence of any of these four starting construction was on September 14th.

And the other three sites are reported done as well.

That's four sites in twelve days. One is a sled, but still!

1000km of supercharger network added in 12 days... freaking awesome! I ❤ Tesla.
 
  • Like
Reactions: bradjc and BenT

BenT

Member
Nov 16, 2015
375
187
Adelaide, SA, Australia
According to supercharge.info, the first evidence of any of these four starting construction was on September 14th.

And the other three sites are reported done as well.

That's four sites in twelve days. One is a sled, but still!

Supercharger.info is a bit off the ball. We know there was construction activity in Adelaide at least on 7 September with temporary fencing and some excavation work visable at this time. Regardless, this is phenomenal work. Hopefully this is a demonstration of what can be accomplished when industry, businesses and governments work together.
 

Chuq

Active Member
Jan 1, 2015
3,229
3,815
Hobart, Tasmania, Australia
Supercharger.info is a bit off the ball. We know there was construction activity in Adelaide at least on 7 September with temporary fencing and some excavation work visable at this time. Regardless, this is phenomenal work. Hopefully this is a demonstration of what can be accomplished when industry, businesses and governments work together.

They update whenever someone lets them know, in this case I was closely monitoring the threads on this forum and sent the update when we were 100% sure it was a Tesla site! So if there had've been an existing permit, I would have sent it in as soon as there was digging. I guess it wasn't strictly a 2 week construction period, but pretty quick none the less :)
 

About Us

Formed in 2006, Tesla Motors Club (TMC) was the first independent online Tesla community. Today it remains the largest and most dynamic community of Tesla enthusiasts. Learn more.

Do you value your experience at TMC? Consider becoming a Supporting Member of Tesla Motors Club. As a thank you for your contribution, you'll get nearly no ads in the Community and Groups sections. Additional perks are available depending on the level of contribution. Please visit the Account Upgrades page for more details.


SUPPORT TMC
Top