Welcome to Tesla Motors Club
Discuss Tesla's Model S, Model 3, Model X, Model Y, Cybertruck, Roadster and More.
Register

Supercharger - Bend, OR - SW. Industrial Way (LIVE Jun 2023, 8 V3 stalls)

This site may earn commission on affiliate links.
Dig ticket filed!
1670471102599.png

1670471152878.png
 
Stopped by today and construction is underway.
View attachment 897983
Thanks for the update. Any chance you can check out the sale/service center to see what they are doing with the dig ticket that was filed last week with construction scheduled to start this week? Should be 4 stalls in the parking lot on the south side of the building off Norwood.

 
Thanks for the update. Any chance you can check out the sale/service center to see what they are doing with the dig ticket that was filed last week with construction scheduled to start this week? Should be 4 stalls in the parking lot on the south side of the building off Norwood.

Could be restricted to just sales/service use. That’s what they did at the new Tigard service center. It’s behind the fence.
 
Pictures
 

Attachments

  • 23C4185D-6120-4B4E-920B-890B4ADDE9FB.jpeg
    23C4185D-6120-4B4E-920B-890B4ADDE9FB.jpeg
    1,022.4 KB · Views: 59
  • 906D08E4-DE6D-4BF0-A7A1-A4466FB3CE77.jpeg
    906D08E4-DE6D-4BF0-A7A1-A4466FB3CE77.jpeg
    768.1 KB · Views: 47
  • E210D07B-96A2-4597-AE3E-AD4E3D65B904.jpeg
    E210D07B-96A2-4597-AE3E-AD4E3D65B904.jpeg
    724.9 KB · Views: 48
  • 4C5E1E1B-301C-425C-847B-30647AF9C58C.jpeg
    4C5E1E1B-301C-425C-847B-30647AF9C58C.jpeg
    883.9 KB · Views: 46
  • 0BCFFBCA-698E-4328-9DBF-5BA16E8E5855.jpeg
    0BCFFBCA-698E-4328-9DBF-5BA16E8E5855.jpeg
    883.9 KB · Views: 48
  • 13218EC5-4FB4-4E57-8072-92EAB8DE9CEC.jpeg
    13218EC5-4FB4-4E57-8072-92EAB8DE9CEC.jpeg
    724.9 KB · Views: 55
Status Monday, Feb 20 3 pm. Electricians were working on the installation. No wires have been run yet but the ropes to pull the wires are in place. The main transformer is not yet on its pad.
 

Attachments

  • AE193FF2-267F-442A-B020-565AA77D4BF5.jpeg
    AE193FF2-267F-442A-B020-565AA77D4BF5.jpeg
    572.4 KB · Views: 49
  • A4A41698-423C-4F0B-9C4B-5B54E208D465.jpeg
    A4A41698-423C-4F0B-9C4B-5B54E208D465.jpeg
    572.4 KB · Views: 51
  • 355A881E-D0E1-4D43-95C6-3A14AFE1C89B.jpeg
    355A881E-D0E1-4D43-95C6-3A14AFE1C89B.jpeg
    747.4 KB · Views: 52
The chargers and their electronics are installed. The transformer is not on site. Once the transformer arrives and gets hooked up, the system will be available. The two week estimate was a bit optimistic.
 

Attachments

  • 79BED262-988C-4690-9997-50E0A568B32F.jpeg
    79BED262-988C-4690-9997-50E0A568B32F.jpeg
    717.4 KB · Views: 43
  • 70CBC61F-A05C-46DD-8E18-43BBD798FA94.jpeg
    70CBC61F-A05C-46DD-8E18-43BBD798FA94.jpeg
    733.6 KB · Views: 47
  • Like
Reactions: bruce4000 and Coign
People installing the sites rarely have accurate insight into the timeline of the utilities feeding power to the site. Their timeline is usually when they are done plus a week for the power to be turned on. They can’t understand how it can take months for some utilities to install a transformer and turn in the power.