FYI, this location failed final inspection on Friday because they did not have a copy of city approved plans posted onsite.
Re-inspection is scheduled for tomorrow!
FYI, this location failed final inspection on Friday because they did not have a copy of city approved plans posted onsite.
Re-inspection is scheduled for tomorrow!
FYI, this location failed final inspection on Friday because they did not have a copy of city approved plans posted onsite.
Re-inspection is scheduled for tomorrow!
And they have now passed the inspection...
Time to drive out there and see when it is powered up -- man this would help with the holiday weekend if it was brought online, but I highly doubt that!
I stopped by on Friday (06/04) around 5-6PM. Still no juice to the meter. It would be great for this location to be live as I've noticed the University area Supercharger is not fully functional.
Looks like Durham, NC was having similar delays, where it appeared that everything was completed but no power. The location was confirmed to have power yesterday but was still off on Monday. Curious if there could be a correlation between that location and ours. Maybe Charlotte is functioning now, or the team that worked on the location will be heading down today. Potentially wishful thinking, but just maybe...