Were they illuminated? It doesn't appear so from this photo but it can be hard to tell during the day. Did you actually plugin and get power?
Cool. I’ll check it out when I’m up there Tuesday. On the 8th no utility work had been done. The utility lines run just south of the building. There is a pole right behind the building near where the charger cabinets will be. So, it’ll be pretty obvious if they’ve worked on that.
It looks like we now have confirmation that these will be V3 superchargers.... Can you update supercharge.info @MarcoRP @Chuq ?
2 charger cabinets, but no switching gear or transformer yet. Obviously no numbers on the stalls. The covers on the cabinets say Tesla Energy.
The public side work is done. It's the utility side transformer that is missing. The meter can is on the rack. If we had a shot 90 degrees to this one I could tell more. I think there just waiting on Dominion at this point. I'm pretty sure those are V3 cabinets. I think they all say Tesla Energy. Thanks for the pic's.
Progress! Transformer installed. Not hooked up at the pole yet though. Wire still spooled at the bottom.