Stopped by this evening to check on progress. Looks like curbs are laid and conduit is run to each charge station termination point.
Swung by last night and it didn't look like there had been much going on the past few days, which isn't surprising given all of the bad weather recently. There are still 10 out of 12 chargers installed with what looks like the remaining 2 units in crates waiting to be opened.
I was there a week ago and it was 10/12 as well so not much progress in the last week apparently. You’re probably right the inclement weather has slowed down the completion. This next upcoming week is forecasted more of the same so it’ll be slow going to finish the project up. So close yet so far! Ski
Well......I noticed this when I was there last week.....drives my OCD crazy.....attention to detail....why does it look like the 3rd charger someone backed into it? This photo really shows it and mine up thread you can see it as well from the other side of the lot. They couldn’t use a level? I guess as long as it works and the electrons flow! On another note we need a dry sunny day to wrap this project up! Ski
The inclement weather has definitely brought this project to a standstill. Checked it out earlier today and it's exactly as it was a week ago. We're supposed to start to thaw out this week so hopefully they'll get back to it and wrap things up.
Frey electric crew back to work today, actual charging equipment is in place, ready to be wired up. Fencing is almost all blown over so got a good look.
@Vol16, Thanks for the update! You’re so close maybe you’ll be the first to charge there when they unleash the hounds! Ski