Looked pretty good today View attachment 657798View attachment 657799
Sweet! could be ready by end of next week. There is a final inspections scheduled on the 4th.
View attachment 657810
I don't see a transformer in the photos. I do see what seems to be an empty concrete pad (to the right of the SC cabinets). It will be a race to get that installed and checked out by the 4th. But hey - "May the fourth be with us"!Sweet! could be ready by end of next week. There is a final inspections scheduled on the 4th.
View attachment 657810
I bet it took less than a week to build based on what I saw when they were first digging in the pad area.How did this go from equipment disappeared, to almost fully installed in the space of a month? And without anyone noticing the return of all the boxed equipment?
Why aren't these chargers working Yet?
Why aren't these chargers working Yet?
Yes... but their bills always come right on time!Getting a transformer from PG&E can take months. IIRC, the wait for a transformer in Newark was 4-6 months.