Does anyone know what is the average built time for a SC is? I mean besides the SD and SJC that took forever, how long does it usually take? According to supercharge.info website, some SC were only in construction 3-4 weeks.
The average number of days between CONSTRUCTION and OPEN status, for the 270 sites for which I have distinct dates for both statuses, is 32.69 days. Of course that number is influenced by how soon someone notices construction....