I think I stumbled across a Supercharger in the permitting process at the North Premium Outlets. L19-00185 - OffSite Permit (OffSite) Primary Applicant is listed as Tesla Energy, along with NV Energy and SIMON CHELSEA LV DEV, LLC
Great find! This location is very near the spaghetti bowl interchange and will probably get a lot of use.
Seems like Chuq and BlueShift missed the call for this one : I’ve just added it on supercharge.info but put 8 stalls as it’s a norm for most Superchargers. Feel free to dm me if you found the right number of stalls. Thanks
Is this the same Supercharger that is being discussed on Reddit? New Las Vegas supercharger looks like it's almost ready to open! : teslamotors
No, this one is different. That location is being discussed here: Supercharger - Las Vegas, NV (Las Vegas Strip)
It looks like Tesla submitted a revised application for this site. It is still in permit status, but it will be a V3 (!!!) supercharger! Hooray! Permit & Application Status "Scope of Work: Updated electrical. Changes to the replacement of V2 Tesla Charging cabinets to Telsa V3 charging cabinets."
Looks like permitting is finally passing. Electrical and tech review both passed in the last week. The permit was issued today, so I presume they'll start work soon.
It appears the permit was issued (or maybe re-issued) today: 19-00185 - OffSite Permit (OffSite) Key Number: 943654 Current Status: Inspections Application Received: 2/5/2019 Project Name: TESLA SUPERCHARGERS - NORTH PREMIUM OUTLETS Address: Parcel: 13933710005 Type of Work: Utility Permit Issued: 12/9/2019 Expiration Date: 12/9/2020 Location Of The Project: GRAND CENTRAL AND BONNEVILLE Scope of Work: NVE PLANS FOR TESLA SUPERCHARGERS - NORTH PREMIUM OUTLETS - GRAND CENTRAL AND BONNEVILLE
Possible construction? I didn't get a picture this morning, but it seems they're working on the parking lot in the NW corner of the site. If you exit NB I-15 at Charleston, and take the exit across for the Alta/Bonneville exit you can see where it looks like they're building a retaining wall, it might also be where they are going to put the SC station. It seemed like the parking lot section is closed (didn't see any cars in that section, only work trucks).
I drove by today and nothing happening. I saw what you said, pallets with cinderblocks for the wall maybe but nothing beyond that. I also didn’t want to pay $8 to go see either. Seems like a horrible spot though. That shopping area is always busy and I’m assuming it’ll be a code to get in like the Linq since it’s paid parking there. We need a SC on the NW side of town. Like Sky Pointe Canyon in the Smith’s parking lot
No visible construction from where I drive past the outlet mall. The area where they were building the retaining wall is completed and I don't see any further sign of construction.
Some fences are up around near the same area where they built the retaining wall before, but facing Alta/Bonneville now. No explicit sign that it is for Tesla SC but that is the only activity I see going on at this site.
Drove by again today. I’m now 90% sure it’s construction for the super charger. Saw 2-3 cabinet-looking things and a backhoe trenching.
I stopped by 17 March and took some pictures from the parking garage. Trench work and pipe work is in the process. You can see the curb structure too. It’s going to be a mess to get to these chargers when done but at least there’s plenty to do once you’re parked and charging. Sorry some of the thumbnail pics aren’t loading...
I ventured out today (14 April 2020) to check status on the build. Doesn’t look like anything has happened, bummer.