It appears that's what is going in now. Take a look at the photo. The pad to the right is where the PG&e equipment will go if I'm not mistaken.
IMG_20200721_162029.jpg
 
  • Like
Reactions: mociaf9

mociaf9

Active Member
Oct 18, 2018
2,881
5,954
CA
Those cabinets are for the power distribution portion. The empty pads are for both Tesla's switchgear (pictured) and the utility transformer (not pictured). So, definite progress but not everything is on site yet.
 

Nosken

Member
Jan 15, 2015
862
751
Lincoln, CA
I was at the site this morning, and they are boring underground from near the large transformer that is along the road to the east. Most likely, this is tapping in to the main underground, and feed the new transformer, that was not on site yet. They seem to be working fairly steadily, now that the elk Grove supercharger is open.
 
  • Like
  • Informative
Reactions: rsg123 and mociaf9

Zimo

Member
Feb 12, 2020
15
10
Lincoln, California
Nice to see all the work going on there. Looks like the time is near after months of inaction. I'll enjoy seeing how fast these V3 chargers are but I doubt I'll use it much as its so close to where I live.
 

SR-75

Member
Nov 19, 2016
171
172
Lincoln, CA
B2BF5EFF-E759-4076-BD47-254F4850BE60.jpeg


The Tesla Switch Gear & Power Distribution Equipment was put in place today. Still waiting for PG&E’s Transformer which should placed just to the left on the empty pad next to Tesla’s Switch Gear in the above picture. Need to watch in the next 6 weeks specially after PG&E’s Transformer shows up here.
 

SR-75

Member
Nov 19, 2016
171
172
Lincoln, CA
The sidewalk next to the transformer across the street is torn up so it looks like the transformer work is in process.

Sidewalk next to the transformer across the street is still torn up. On the road next to it, the hole was filled and repaved or patched.
unable to upload picture on this post. will try in a separate post.
 

SR-75

Member
Nov 19, 2016
171
172
Lincoln, CA
The sidewalk next to the transformer across the street is torn up so it looks like the transformer work is in process.

Sidewalk next to the transformer across the street is still torn up. On the road next to it, the hole was filled and repaved or patched.

IMG_4880 2.jpeg
IMG_0630.jpeg


Good news!!!

Noticed today that our PG&E Transformer was installed sometime this last week. Thats our Tesla in the picture.
The Superchargers are not powered up as yet. Need to keep watch for more activity here for power up Time and testing.
 

SR-75

Member
Nov 19, 2016
171
172
Lincoln, CA
IMG_8155.JPG
IMG_8655.JPG


Was here checking on this, this afternoon.
Sidewalk next to the transformer across the street has been paved, but not set yet.
We still do NOT have power to our Tesla V3 Superchargers as yet. It looks likes this will be completed anytime now.
 
  • Like
Reactions: mociaf9

SR-75

Member
Nov 19, 2016
171
172
Lincoln, CA
This Supercharger just popped up on my Tesla App and on our in car's Teals's Map as "Lincoln, CA - Groveland Lane".
In our car's Tesla Map it shows this site as 250kW... It is official now.

Thanks bmah for alerting @MarcoRP ...
 
  • Like
Reactions: MarcoRP

MarcoRP

Well-Known Member
Sep 6, 2017
5,209
10,798
Montréal
This Supercharger just popped up on my Tesla App and on our in car's Teals's Map as "Lincoln, CA - Groveland Lane".
In our car's Tesla Map it shows this site as 250kW... It is official now.

Thanks bmah for alerting @MarcoRP ...
What’s really stunning is that this location is now open exactly 365 days after having been added on Supercharge Info. lol
6829507E-A170-4CA4-9B98-B09EB9A1CC7E.jpeg
 

Speight

Member
Jan 20, 2016
143
169
SF Bay Area, CA
Any idea why those UK locations have been in “Construction “ for 2 years? Any Idea what the holdup is?
You're not the only one to ask (and it's actually been almost four years now): Reddit post
Short answer: Tesla started construction on the site before ensuring they had sufficient power supply, and they apparently couldn't convince the neighbors to let them upgrade the lines through their properties. There must be existing electrical power to the location to serve the other businesses located there (unless they are all on generator power!), but I guess it doesn't have enough capacity for multiple fast chargers.
So if you think the Lincoln SC taking a year was a long time, things could be much worse.
 

Products we're discussing on TMC...

About Us

Formed in 2006, Tesla Motors Club (TMC) was the first independent online Tesla community. Today it remains the largest and most dynamic community of Tesla enthusiasts. Learn more.

Do you value your experience at TMC? Consider becoming a Supporting Member of Tesla Motors Club. As a thank you for your contribution, you'll get nearly no ads in the Community and Groups sections. Additional perks are available depending on the level of contribution. Please visit the Account Upgrades page for more details.


SUPPORT TMC
Top