    Hello all,

    First post here. We just got our new Model X a couple of weeks ago and are very excited! Looks like you all have a great community going. We are excited to be part of it.

    Does anyone have any info on the status of the Mackinaw City, MI supercharger?

    We live around Traverse City, MI and are planning on visiting Minneapolis in early June of this year. Currently this would require us to either 1) stay overnight/take an extended stop somewhere to destination charge 2) go through Chicago. If either the Mackinaw City supercharger or the Escanaba supercharger become operational by early June we can shoot through the UP.

    Thanks.
     
    • Like x 1
  2. mrau

    mrau Authorized Driver

    Joined:
    Nov 12, 2018
    Messages:
    383
    Location:
    Mid-Michigan
    Welcome to the group @michiganwoods . Haven't heard much about the Mackinaw SC, but I hope the ones planned for Michigan get started soon, we sure could use them.

    Also, I did see this meet up posted on the Michigan Group of the TMC that may be close to you. A bit far for me to drive, but it sounds like fun.

    here is the link:
    Event: Tesla Enthusiasts of Northern Michigan Breakfast

    "Breakfast get together of Tesla Enthusiasts at Cafe Sante in Boyne City, Michigan at 930 A.M. on Saturday 13 April 2019.
    This is a first meeting of this group to discuss issues of intetest."



    The Michigan Group on TMC is free to join if you have not done so. Lots of good post there too.

    https://teslamotorsclub.com/tmc/groups/23/overview
     
  3. IT Geek

    IT Geek Member

    Joined:
    Nov 16, 2016
    Messages:
    899
    Location:
    Michigan
    I wouldn't bet on either of them being available in June. Unfortunately we've been waiting on the Escanaba one for quite some time. Rumor is that Escanaba construction starts this year in April. However, they've been rather slow getting everything in place (on the electrical equipment side) once the construction has begun. I think Gaylord sat there for months and months waiting for the transformer to get installed.

    But you could always do like I did and charge up in Gaylord, then put on some miles at one of the many Destination chargers in Mackinaw City and then make a go across the UP all in one charge. I did that last year in my 90D. Not for the faint of heart though.... :)

    Supercharger - Escanaba, MI

    There is a hotel in Naubinway with a Destination Charger if you want to stop there overnight. Not a bad plan, to be honest.

    Anyway, welcome to the Tesla family. This is indeed a very thriving community.
     
    • Like x 1
  4. michiganwoods

    michiganwoods New Member

    Joined:
    Apr 3, 2019
    Messages:
    3
    Location:
    Cedar, MI
    @mrau Thank you for the welcome and the links!

    @IT Geek the one charge across the UP sounds daring. I don't think I want to try that. Naubinway sounds like a solid option -- unfortunate you need to stay overnight. Someone else showed me a way to do it but it involves 4+ hours of charging total. So that's another option that avoids the overnight (but has you waiting more).
     
  5. IT Geek

    IT Geek Member

    Joined:
    Nov 16, 2016
    Messages:
    899
    Location:
    Michigan
    Yeah, it's all a trade when you get off the Supercharger network. For example, you could even drive to Ludington and take the ferry....but that's not cheap and takes several hours as well.

    Unfortunately the UP is going to be a bit of a challenge until they get a SC up and running up there. Until then...any plans will incur several hours of waiting unless you feel you can make 260 miles in one charge. Probably not advisable in a Model X.
     
    • Like x 1
  6. gonzo

    gonzo Member

    Joined:
    Jun 1, 2017
    Messages:
    18
    Location:
    North Carolina
    Good News!

    Was just in Mackinaw City on Sat. October 5. Tesla Superchargers now under construction at 801 South Huron Avenue, Mackinaw City MI 49701
    @BlueShift

    Note: There are two Tesla Destination Stations + one Nema 14-50 Station at this location. All located at the water's edge to the left of the Ticket Office for Star Line Mackinaw Island Ferry. Phone Number for the office: 800-638-9892 Exceptionally nice folks work here. The owner of Star Line has a Model X 100D. Did not meet him.
    I have a 2016 Tesla Model S 90D and got 30 mph @40a, 242v charge rate using one of the Tesla Destination Stations. See PlugShare for more info,
    especially the comments.

    10 pictures below. This is all the information that I have about these Superchargers.


    IMG_0890.jpeg IMG_0891.jpeg IMG_0895.jpeg IMG_0896.jpeg IMG_0897.jpeg IMG_0899.jpeg IMG_0901.jpeg IMG_0902.jpeg IMG_0903.jpeg IMG_0904.jpeg



     
    • Like x 11
    • Informative x 9
    • Love x 1
  7. sdoorex

    sdoorex Member

    Joined:
    Feb 25, 2015
    Messages:
    263
    Location:
    Front Range, CO
    • Helpful x 1
    • Like x 1
  8. ItsNotAboutTheMoney

    ItsNotAboutTheMoney Well-Known Member

    Joined:
    Jul 12, 2012
    Messages:
    10,212
    Location:
    Maine
    Mackinaw City, MI

    Along Primary Interstates: I-75
    Along US Numbered Highways (<=5mi): US-23
    Along Auxiliary Interstates: None

    I-75

    From: Gaylord, MI - 58.8 miles
    To: Sault Ste. Marie, MI (Permit) - 55.4 miles
    Diversion: 1.2 miles
    From: Bay City, MI - 175.4 miles
    To: End (Canada at Sault Ste Marie, MI) - 57.3 miles

    To: Sault Ste Marie, ON (Construction) (I-75, l, ON-550) - 62.3 miles
    To: Sudbury, ON (I-75, l, TCH/ON-17) - 250.1 miles

    From: Clare, MI (US-127, I-75) - 143.9 miles
    From: Cadillac, MI (US-131, MI-32, I-75) - 134.3 miles
    From: Escanaba, MI ("Permit") (US-2, I-75) - 146.8 miles
    From: Howard, WI (I-41, US-41, US-2, I-75) - 254.9 miles

    Splits a 113.2 mile gap between Gaylord, MI and Sault Ste. Marie, ON, and provides better options for driving from Southwestern and Southern Michigan to the Upper Pensinsula and North Ontario. Also, if Escanaba, MI is ever built, it'll allow easier looping around the Upper Peninsula.

    With this, I think Tesla won't be building the Sault Ste. Marie, MI Supercharger.
     
    • Disagree x 1
  9. Big Earl

    Big Earl bnkwupt

    Joined:
    Jul 12, 2017
    Messages:
    4,886
    Location:
    Springfield, VA
    V3. :cool:
     
    • Like x 4
  10. IT Geek

    IT Geek Member

    Joined:
    Nov 16, 2016
    Messages:
    899
    Location:
    Michigan
    I was going to say that pad looked a bit too small to fit 4 cabinets.... :)
     
  11. 79yofridge

    79yofridge Member

    Joined:
    Mar 16, 2019
    Messages:
    26
    Location:
    Michigan
    Yes!! Thank you!! :D
     
  12. Big Earl

    Big Earl bnkwupt

    Joined:
    Jul 12, 2017
    Messages:
    4,886
    Location:
    Springfield, VA
    That pad will be for the switchgear and two auto transformers. The two charging cabinets will be mounted on pads that have yet to be poured... you can see the bundle of conduits for one of the charging cabinets sticking out of the ground in one of the pictures.
     
    • Informative x 2
  13. emupilot

    emupilot Active Member

    Joined:
    May 23, 2013
    Messages:
    1,439
    Location:
    Northern California
    Since there isn't anything labeled as Tesla in the photos, I checked building permits and indeed there is a permit listing for a "Tesla charging station" at 801 S Huron Ave dated May 9, 2019.
     
    • Like x 2
  14. IT Geek

    IT Geek Member

    Joined:
    Nov 16, 2016
    Messages:
    899
    Location:
    Michigan
    Yep, you're right (as usual when it comes to these things) :)

    I have to head up to Traverse City at the end of the month, so unless they work at breakneck speed (and then steal pedestals from somewhere else) I'm going to miss this one until 2020. Hopefully they do work fast though, because as we all know...winter is coming. :)
     
  15. MarcoRP

    MarcoRP @MontrealTesla

    Joined:
    Sep 6, 2017
    Messages:
    4,846
    Location:
    Montréal
    Question. Is this Supercharger in Mackinaw or in Mackinac? Are they pronounced the same way?
     
    • Funny x 2
  16. sdoorex

    sdoorex Member

    Joined:
    Feb 25, 2015
    Messages:
    263
    Location:
    Front Range, CO
    They are pronounced the same (MAK-in-aw) but Mackinac is the island whereas Mackinaw is the township on the lower peninsula from which you can take a ferry to the island. You can also take a ferry from St. Ignace on the upper peninsula which is across the Mackinac Bridge and straight from Mackinaw City.

    The island would be an odd place for a supercharger as they don't allow typical passenger vehicles, only a few emergency vehicles and snowmobiles, instead everyone on the island walks, bikes, or uses horse drawn carriage. Eventually it could get L2 chargers when they convert their emergency vehicles to EVs.
     
    • Like x 5
    • Helpful x 1
  17. Bigsam411

    Bigsam411 Member

    Joined:
    Jul 15, 2019
    Messages:
    25
    Location:
    Canton Michigan
    Wow I was here a couple weeks ago with my Model 3. I elected to not use the Level 2 chargers at this parking lot as I didn't feel like spending $10 to park here (I had free parking at the hotel next door) and I had enough range to get back to Gaylord Supercharger.

    Glad to see some progress here. Now if only they would finish the Swartz Creek one so I can have a stop between me and Frankenmuth and then start the Novi one so I can have another option in case of emergencies near me.
     
    • Like x 1
  18. FalconAndy

    FalconAndy Member

    Joined:
    Sep 16, 2019
    Messages:
    11
    Location:
    Midland, MI
    Any idea of a completion date? This is great news!
     
  19. IT Geek

    IT Geek Member

    Joined:
    Nov 16, 2016
    Messages:
    899
    Location:
    Michigan
    I'll be surprised if it is done this year, but no one here that doesn't work for Tesla would have any idea... Too many variables to predict that sort of thing.
     
  20. FalconAndy

    FalconAndy Member

    Joined:
    Sep 16, 2019
    Messages:
    11
    Location:
    Midland, MI
    Well it looks like they have made some progress based on the pictures. It’ll be very nice to have it when it’s done
     

Share This Page

  • About Us

    Formed in 2006, Tesla Motors Club (TMC) was the first independent online Tesla community. Today it remains the largest and most dynamic community of Tesla enthusiasts. Learn more.
  • Do you value your experience at TMC? Consider becoming a Supporting Member of Tesla Motors Club. As a thank you for your contribution, you'll get nearly no ads in the Community and Groups sections. Additional perks are available depending on the level of contribution. Please visit the Account Upgrades page for more details.


    SUPPORT TMC