STDRDC13
Member
Two utility poles have been set with 500kVa atop each serving the 2 prefabs.
Contractors will now need to run conduit from switchgear to their respective utility pole. Same setup as the SuC just south of this location.
Contractors will now need to run conduit from switchgear to their respective utility pole. Same setup as the SuC just south of this location.