Supercharger - Somerville, MA

This site may earn commission on affiliate links.
Trench is cut and mostly excavated. No cabinets etc on site yet. I found the template for organizing the conduit coming into the cabinets kind of interesting. I wonder if Tesla supplies this as a part of their efforts to streamline SC construction? Looks like the team made a plywood copy of it.
 

Attachments

  • 63FF744A-01AD-48D8-B8AC-4DC52ED8171C.jpeg
    63FF744A-01AD-48D8-B8AC-4DC52ED8171C.jpeg
    515.8 KB · Views: 246
  • 6D64C927-6CB8-4136-85E2-EA02539A3122.jpeg
    6D64C927-6CB8-4136-85E2-EA02539A3122.jpeg
    848.9 KB · Views: 169
  • 0AA3DABE-CE11-4015-86E8-D969C010C1A0.jpeg
    0AA3DABE-CE11-4015-86E8-D969C010C1A0.jpeg
    727.1 KB · Views: 152
Trench is cut and mostly excavated. No cabinets etc on site yet. I found the template for organizing the conduit coming into the cabinets kind of interesting. I wonder if Tesla supplies this as a part of their efforts to streamline SC construction? Looks like the team made a plywood copy of it.
On site
 

Attachments

  • 25068417-EAF4-48F0-BB56-02CC3F190913.jpeg
    25068417-EAF4-48F0-BB56-02CC3F190913.jpeg
    728.5 KB · Views: 148
Turns out the trench has actually been done this whole time even though it only look half excavated. It terminates amongst the pedestal row to a utility pole. Conduit pipe is in place.
 

Attachments

  • 16D5A91C-1FE2-4361-B540-DE956DCEEA52.jpeg
    16D5A91C-1FE2-4361-B540-DE956DCEEA52.jpeg
    988.8 KB · Views: 106
  • 57A6760E-E640-449E-9F54-3419B9713BC3.jpeg
    57A6760E-E640-449E-9F54-3419B9713BC3.jpeg
    731.3 KB · Views: 95
  • DC5867B1-0A2D-44CF-A296-9681C143B171.jpeg
    DC5867B1-0A2D-44CF-A296-9681C143B171.jpeg
    899.5 KB · Views: 98
Conduit pipes are all in. Two on the bottom cemented into place from the pole to transformer location. Pipes from cabinets out to each stall run back across the top of the same trench. Some sand fill going in as construction progresses. Interesting the way the conduit is getting from the trench to stalls - hard to get a good photo but it looks strange in person.
 

Attachments

  • 8B12482B-9E2F-445A-84F7-44E4FEDB58B2.jpeg
    8B12482B-9E2F-445A-84F7-44E4FEDB58B2.jpeg
    714.9 KB · Views: 93
  • 690E1145-F779-4AC2-B899-22F11EB5FBB1.jpeg
    690E1145-F779-4AC2-B899-22F11EB5FBB1.jpeg
    708.7 KB · Views: 94
  • 36543BBA-E637-4AAC-985C-A88BC66CA3DC.jpeg
    36543BBA-E637-4AAC-985C-A88BC66CA3DC.jpeg
    836.4 KB · Views: 89
  • Like
Reactions: Koolio46 and kayak1
Rebar for the pedestal bases is in. Cement for the bollards and what looks like two street lights is in as well. I think we’ll have Tesla charging signs at this location based on the posts being setup in the concrete.
Interesting that they're not using the pre-formed pedestal bases. I assumed they were doing that at all sites now, except those using the new drop-in prefab superchargers.