DMC5180
Member
Awesome, Thank You so much for the great work you do. Have you done any other sites in Wisconsin or Minnesota recently?I'm the builder on the site. Meter install timing varies wildly from jurisdiction to jurisdiction. Since this meter is mounted on the transformer itself, and not a stand, the utility company installs the base as well as the meter. First time (out of around 30 builds) we've had the transformer show up with the full meter mounted. WPS has really been on the ball, and a pleasure to work with. I have personally had a project take up to nine months to install trans and meter. Kudos to WPS.