I did some sleuthing around North Stamford, CT looking for any obvious construction around the junctions of the Merritt Parkway and Long Ridge Road and High Ridge Road. I found nothing in the immediate areas of either of those.. but about 2.5 miles down High Ridge Road from the Merritt (near Bull's Head Diner), I found this construction site in the rear parking lot of Lord and Taylor:

upload_2017-6-30_15-9-34.png


I got a little closer, and they're definitely building something power related with lots of curbs:

upload_2017-6-30_15-11-54.png


I did not see any Tesla related materials (yet).

Here's a google map of the parking area: Google Maps

So, while it's not exactly North Stamford or Stamford (near I-95), it could be the site of a larger SC location in the works. Or could be entirely unrelated construction, like a staging area for some other project. It's a pretty good area, with some restaurants, CVS, banks, hotel, etc within walking distance. It's only about 5-7 minutes from the Merritt, which to compare, is a lot better than the SC in Woodbridge, VA at the Potomac Mills Mall, which is not easy or fast to get to from 95.

Next time I'm in Stamford during the week, I plan to go to the P&Z office to see if I can track down any more info.
 
It does look like parts for some kind of electricity related project. The Tesla specific parts might still be in the trailers.

Tesla has built enough superchargers now, they probably put together SC kits that load into X number of semi trailers with all the components needed.
 
Well Hank, you found something, that's a start. Based on the photos it doesn't look like any supercharger install I've seen so far though. Who knows, maybe it's going to be for a VERY high power supercharger with all that utility looking equipment.
 
Here is an update on the status of North American "Coming Soon" superchargers. There were by my count 283 on the Find Us page as of April 24th which claimed to have a target opening date in 2017. 11 stations came online in May and 10 in June (including expansions), which is a pace which would complete about 30% of Tesla's ambitious 2017 supercharger network expansion plans. Below is a list of the 10 sites that came online in June and the 40 sites for which we have information or at least rumors on their location. The pace of openings will soon increase, as right now the number of sites in permitting and under construction is about as high as it has ever been.

LocationSite Known?Status
Barstow, CA yes expansion operational
Burbank II, CA yes under construction
Cabazon, CA yes expansion operational
Fountain Valley, CA yes expansion in design/permitting
Fremont, CA yes under construction hiatus
Rocklin, CA yes expansion under construction
Sacramento, CA yes in permitting
Vacaville, CA yes expansion under construction
Yermo, CA yes in permitting
Florida City, FL yes operational
Dows, IA yes operational
Chicago - Lakeshore East, IL yes under construction
Rolling Meadows, IL yes in permitting
Emporia, KS yes in design / permitting
Leominster, MA yes under construction
Aberdeen, MD yes under construction
La Vale, MD yes under construction
North East, MD yes under construction
Lansing, MI yes construction imminent?
Ludington, MI yes operational
Marshall, MI yes under construction
Traverse City, MI yes in permitting
Osage Beach, MO yes operational
Truth or Consequences, NM yes under construction
Erwin, NY yes under construction
New Rochelle, NY yes in permitting
Victor, NY yes operational
Cambridge, OH yes under construction
Breezewood, PA yes awaiting transformer
Falls Creek, PA yes under construction
Bristol, TN yes operational
Austin (North Loop), TX yes under construction hiatus
Dallas, TX yes in permitting
McAllen, TX yes awaiting reconstruction
St George, UT yes expansion operational
Charlottesville, VA yes awaiting transformer
Arlington, WA yes operational
Sequim, WA yes awaiting power on / testing
Snoqualmie, WA maybe in design / permitting
Green Bay (Howard), WI yes under construction
Beckley, WV yes in design / permitting
Charleston, WV yes operational
Morgantown, WV yes under construction
Weston, WV yes under construction
Evanston, WY yes under construction
Laramie, WY no in permitting
Rawlins, WY yes in design / permitting
Rock Springs, WY yes awaiting power on / testing
Nanaimo, BC yes awaiting transformer
LTvis, QC yes under construction

Just for fun, below are the remaining 222 sites for which we need to sleuth out information:
Montgomery AL, Oxford AL, Steele AL, Phoenix AZ, Tucson AZ, Willcox AZ, Baker CA, Bakersfield II CA, Calabasas CA, Carlsbad CA, Commerce CA, Concord CA, Corona CA, Cupertino CA, Daly City CA, Denver II CA, Downey CA, El Cajon CA, Emeryville CA, Fairfield CA, Folsom III CA, Fresno II CA, Glendale CA, Hayward CA, Hesperia CA, Hollywood CA, Irvine CA, La Jolla CA, Lake Elsinore CA, Laytonville CA, Lone Pine II CA, Long Beach CA, Marin City CA, Napa II CA, Northridge CA, Palm Desert CA, Pasadena CA, Petaluma II CA, Pomona CA, Redding CA, Redondo Beach CA, Roseville II CA, Salinas CA, San Bernardino CA, San Clemente CA, San Felipe CA, San Francisco (Financial Dist) CA, San Francisco (Mission) CA, San Francisco (SOMA) CA, San Jose CA, San Luis Obispo CA, San Mateo (Hillsdale) CA, San Mateo II CA, San Rafael CA, San Ramon CA, Santa Barbara CA, Santa Clarita CA, Santa Cruz CA, Santa Monica CA, Sherman Oaks CA, Stockton CA, Sunnyvale CA, Thousand Oaks CA, Vallejo CA, Vista CA, Alamosa CO, Aspen CO, Boulder CO, Estes Park CO, Lone Tree II CO, Poncha Springs CO, Danbury CT, Darien III CT, North Stamford CT, Old Lyme CT, Stamford CT, Torrington CT, Trumbull CT, West Hartford II CT, Washington DC, Rehoboth Beach DE, Altamont Springs FL, Aventura FL, Boca Raton FL, Fort Myers FL, Live Oak FL, Miami (Brickell) FL, Miami (Wynwood) FL, Orlando FL, Sarasota FL, St. Petersburg FL, West Melbourne FL, West Palm Beach FL, Atlanta III GA, Buford GA, Madison GA, Honolulu HI, Altoona IA, Shelby IA, Sioux City IA, Chicago (Lincoln Park) IL, Chicago III IL, Fort Wayne IN, Colby KS, New Orleans LA, Beverly MA, Boston MA, Braintree MA, Lynnfield MA, Mansfield MA, Natick MA, Orleans MA, Seekonk MA, Wareham MA, Beltsville MD, Gaithersburg MD, Grasonville MD, Halethorpe MD, National Harbor MD, Freeport ME, Auburn Hills MI, Livonia MI, St. Clair Shores MI, Alexandria MN, Minneapolis MN, Rochester MN, Kansas City MO, St. Louis MO, Grenada MS, Hattiesburg MS, Greensboro NC, Raleigh NC, Statesville NC, Fargo ND, North Conway NH, Barnegat Township NJ, Florence NJ, Hackensack NJ, Jersey City NJ, Mount Laurel NJ, Newark NJ, Paramus NJ, Parsippany-Troy Hills NJ, Woodbridge NJ, Deming NM, Socorro NM, Stateline NV, Brooklyn (Williamsburg) NY, Brooklyn II NY, Clinton Corners NY, Hicksville NY, Islandia NY, Lower Manhattan NY, Manhattan (Midtown) NY, Manhattan III NY, Manorville NY, Queens NY, Yonkers NY, Toledo OH, Boardman OR, Portland OR, Springfield II OR, Tigard OR, Bellefonte PA, King of Prussia PA, North Huntingdon PA, Philadelphia PA, West Middlesex PA, Charleston SC, Florence SC, Sioux Falls SD, Cookeville TN, Dickson TN, Nashville II TN, Austin (Downtown) TX, Dilley TX, Fort Stockton TX, Fort Worth TX, Fredericksburg TX, Grapevine TX, Houston II TX, Italy TX, Laredo TX, Nacogdoches TX, Pecos TX, Plano TX, San Antonio TX, Wichita Falls TX, Fairfax VA, Richmond VA, Tysons VA, Bellevue WA, Lynnwood WA, Okanogan WA, Olympia WA, Seattle WA, Wenatchee WA, Madison II WI, Milwaukee WI, Oshkosh WI, Sturgeon Bay WI, Wheatland WY, Calgary AB, Edmonton AB, Sicamous BC, Tsawwassen BC, Vancouver BC, Barrie II ON, Belleville ON, Cambridge ON, Concord ON, Hamilton ON, Markham ON, Mississauga (Meadowvale) ON, Mississauga II ON, North York ON, Ottawa ON, Owen Sound ON, Pickering ON, Renfrew ON, St. Catherines ON, Stardale ON, Sudbury ON, Toronto ON, Vaughan ON, Brossard QC, Drummondville QC, Laval QC, Point-Claire QC, Saguenay QC, Saint Therese QC, Trois-Rivieres QC
 
Here is an update on the status of North American "Coming Soon" superchargers. There were by my count 283 on the Find Us page as of April 24th which claimed to have a target opening date in 2017. 11 stations came online in May and 10 in June (including expansions), which is a pace which would complete about 30% of Tesla's ambitious 2017 supercharger network expansion plans. Below is a list of the 10 sites that came online in June and the 40 sites for which we have information or at least rumors on their location. The pace of openings will soon increase, as right now the number of sites in permitting and under construction is about as high as it has ever been.

LocationSite Known?Status
Barstow, CA yes expansion operational
Burbank II, CA yes under construction
Cabazon, CA yes expansion operational
Fountain Valley, CA yes expansion in design/permitting
Fremont, CA yes under construction hiatus
Rocklin, CA yes expansion under construction
Sacramento, CA yes in permitting
Vacaville, CA yes expansion under construction
Yermo, CA yes in permitting
Florida City, FL yes operational
Dows, IA yes operational
Chicago - Lakeshore East, IL yes under construction
Rolling Meadows, IL yes in permitting
Emporia, KS yes in design / permitting
Leominster, MA yes under construction
Aberdeen, MD yes under construction
La Vale, MD yes under construction
North East, MD yes under construction
Lansing, MI yes construction imminent?
Ludington, MI yes operational
Marshall, MI yes under construction
Traverse City, MI yes in permitting
Osage Beach, MO yes operational
Truth or Consequences, NM yes under construction
Erwin, NY yes under construction
New Rochelle, NY yes in permitting
Victor, NY yes operational
Cambridge, OH yes under construction
Breezewood, PA yes awaiting transformer
Falls Creek, PA yes under construction
Bristol, TN yes operational
Austin (North Loop), TX yes under construction hiatus
Dallas, TX yes in permitting
McAllen, TX yes awaiting reconstruction
St George, UT yes expansion operational
Charlottesville, VA yes awaiting transformer
Arlington, WA yes operational
Sequim, WA yes awaiting power on / testing
Snoqualmie, WA maybe in design / permitting
Green Bay (Howard), WI yes under construction
Beckley, WV yes in design / permitting
Charleston, WV yes operational
Morgantown, WV yes under construction
Weston, WV yes under construction
Evanston, WY yes under construction
Laramie, WY no in permitting
Rawlins, WY yes in design / permitting
Rock Springs, WY yes awaiting power on / testing
Nanaimo, BC yes awaiting transformer
LTvis, QC yes under construction

Just for fun, below are the remaining 222 sites for which we need to sleuth out information:
Montgomery AL, Oxford AL, Steele AL, Phoenix AZ, Tucson AZ, Willcox AZ, Baker CA, Bakersfield II CA, Calabasas CA, Carlsbad CA, Commerce CA, Concord CA, Corona CA, Cupertino CA, Daly City CA, Denver II CA, Downey CA, El Cajon CA, Emeryville CA, Fairfield CA, Folsom III CA, Fresno II CA, Glendale CA, Hayward CA, Hesperia CA, Hollywood CA, Irvine CA, La Jolla CA, Lake Elsinore CA, Laytonville CA, Lone Pine II CA, Long Beach CA, Marin City CA, Napa II CA, Northridge CA, Palm Desert CA, Pasadena CA, Petaluma II CA, Pomona CA, Redding CA, Redondo Beach CA, Roseville II CA, Salinas CA, San Bernardino CA, San Clemente CA, San Felipe CA, San Francisco (Financial Dist) CA, San Francisco (Mission) CA, San Francisco (SOMA) CA, San Jose CA, San Luis Obispo CA, San Mateo (Hillsdale) CA, San Mateo II CA, San Rafael CA, San Ramon CA, Santa Barbara CA, Santa Clarita CA, Santa Cruz CA, Santa Monica CA, Sherman Oaks CA, Stockton CA, Sunnyvale CA, Thousand Oaks CA, Vallejo CA, Vista CA, Alamosa CO, Aspen CO, Boulder CO, Estes Park CO, Lone Tree II CO, Poncha Springs CO, Danbury CT, Darien III CT, North Stamford CT, Old Lyme CT, Stamford CT, Torrington CT, Trumbull CT, West Hartford II CT, Washington DC, Rehoboth Beach DE, Altamont Springs FL, Aventura FL, Boca Raton FL, Fort Myers FL, Live Oak FL, Miami (Brickell) FL, Miami (Wynwood) FL, Orlando FL, Sarasota FL, St. Petersburg FL, West Melbourne FL, West Palm Beach FL, Atlanta III GA, Buford GA, Madison GA, Honolulu HI, Altoona IA, Shelby IA, Sioux City IA, Chicago (Lincoln Park) IL, Chicago III IL, Fort Wayne IN, Colby KS, New Orleans LA, Beverly MA, Boston MA, Braintree MA, Lynnfield MA, Mansfield MA, Natick MA, Orleans MA, Seekonk MA, Wareham MA, Beltsville MD, Gaithersburg MD, Grasonville MD, Halethorpe MD, National Harbor MD, Freeport ME, Auburn Hills MI, Livonia MI, St. Clair Shores MI, Alexandria MN, Minneapolis MN, Rochester MN, Kansas City MO, St. Louis MO, Grenada MS, Hattiesburg MS, Greensboro NC, Raleigh NC, Statesville NC, Fargo ND, North Conway NH, Barnegat Township NJ, Florence NJ, Hackensack NJ, Jersey City NJ, Mount Laurel NJ, Newark NJ, Paramus NJ, Parsippany-Troy Hills NJ, Woodbridge NJ, Deming NM, Socorro NM, Stateline NV, Brooklyn (Williamsburg) NY, Brooklyn II NY, Clinton Corners NY, Hicksville NY, Islandia NY, Lower Manhattan NY, Manhattan (Midtown) NY, Manhattan III NY, Manorville NY, Queens NY, Yonkers NY, Toledo OH, Boardman OR, Portland OR, Springfield II OR, Tigard OR, Bellefonte PA, King of Prussia PA, North Huntingdon PA, Philadelphia PA, West Middlesex PA, Charleston SC, Florence SC, Sioux Falls SD, Cookeville TN, Dickson TN, Nashville II TN, Austin (Downtown) TX, Dilley TX, Fort Stockton TX, Fort Worth TX, Fredericksburg TX, Grapevine TX, Houston II TX, Italy TX, Laredo TX, Nacogdoches TX, Pecos TX, Plano TX, San Antonio TX, Wichita Falls TX, Fairfax VA, Richmond VA, Tysons VA, Bellevue WA, Lynnwood WA, Okanogan WA, Olympia WA, Seattle WA, Wenatchee WA, Madison II WI, Milwaukee WI, Oshkosh WI, Sturgeon Bay WI, Wheatland WY, Calgary AB, Edmonton AB, Sicamous BC, Tsawwassen BC, Vancouver BC, Barrie II ON, Belleville ON, Cambridge ON, Concord ON, Hamilton ON, Markham ON, Mississauga (Meadowvale) ON, Mississauga II ON, North York ON, Ottawa ON, Owen Sound ON, Pickering ON, Renfrew ON, St. Catherines ON, Stardale ON, Sudbury ON, Toronto ON, Vaughan ON, Brossard QC, Drummondville QC, Laval QC, Point-Claire QC, Saguenay QC, Saint Therese QC, Trois-Rivieres QC
Thanks for your efforts, there seems to be room at both Napa and Petaluma not sure they will expand or do new. San Rafael has 20 level 2 chargers at the Target, wondering if they will install there.
 
I've looked through electrical permits in Toledo and can not find any that would fit the bill. For argument/rumor/conversation I will venture a guess that the new Toledo, Oh location will be located at the Meijer store on the corner of Alexis and Hagman just south of the MI/OH line. In addition to the Meijer Store (as a corporation they host at least 8 locations) there are several fast food outlets and easy access to I-75. This would catch travelers from the east (Cleveland, Macedonia)on I-280 heading toward Detroit without sending them a bit out of the way through Maumee. It would also be an alternative for the N-S I-75 traffic that must use Maumee.
 
There is still missing a Supercharger location on CA-140 between Merced, CA and Yosemite National Park. This route is usually open all year vs the CA-120.

My wife prefers the CA-140 route because she is more comfortable not seeing the deep cliff view from the passenger side when on the CA-120 route.
 
I think you are forgetting the 25 in Canada and 1 in Mexico (at least I'm guessing that isn't in the USA count). So according to supercharge.info today there are 372 superchargers in North America, and so far 11 new ones this year. That's 361 to be doubled in 2017. That's one per day, with an allowance for one missed day per quarter.

I sure hope they have a clear plan to achieve this, as it seems a real stretch to me. The hard part so far has been permitting and getting the utilities to do their bit; accelerating those things won't be simple. Perhaps they mean to change direction and deploy a whole bunch to two slot "temporary" superchargers? Even so they don't seem to have solved the slow charging problem, and there's the hint that a new generation of superchargers is coming soon. This is a real puzzle.

And yes, they're way off the pace.

So we're past the halfway point of 2017. How's Tesla doing on its promised doubling of North American supercharger locations (see their February 2017 letter to shareholders)?

Well, they've picked up the pace a little bit lately, but it still looks utterly hopeless. As of June 30 they had reached 398 locations operational. That's 37 new locations this year over the 361 locations they started with. In 181 days. To reach their goal they needed to open just about one new location per day.

They've opened five more in July so far, but that's still not close to one a day. As it stands, for the rest of the year they'll have to open new supercharger locations at the rate of 1.8+ per day to make their goal. I don't think that's going to happen.
 
So we're past the halfway point of 2017. How's Tesla doing on its promised doubling of North American supercharger locations (see their February 2017 letter to shareholders)?

Well, they've picked up the pace a little bit lately, but it still looks utterly hopeless. As of June 30 they had reached 398 locations operational. That's 37 new locations this year over the 361 locations they started with. In 181 days. To reach their goal they needed to open just about one new location per day.

They've opened five more in July so far, but that's still not close to one a day. As it stands, for the rest of the year they'll have to open new supercharger locations at the rate of 1.8+ per day to make their goal. I don't think that's going to happen.
How many existing locations have had more plugs added?
 
This is why I think "locations" must mean "pedestals." Opening a few more of these 40-stall sites like Kettleman City will make a dent in their promise.

And they might miss. ;)

The words mean what they mean, not something else. In this blog post from April Tesla refers to the individual pedestals as Superchargers. The quote from the shareholder letter refers to Supercharger locations. Different things. Either way they are way, way behind. I don't see how they can achieve what they said they would.
 
  • Informative
Reactions: Rocky_H
The words mean what they mean, not something else. In this blog post from April Tesla refers to the individual pedestals as Superchargers. The quote from the shareholder letter refers to Supercharger locations. Different things. Either way they are way, way behind. I don't see how they can achieve what they said they would.
I am skeptical they'll reach their goal, too. It'll be interesting to see how close they come.
 
The words mean what they mean, not something else. In this blog post from April Tesla refers to the individual pedestals as Superchargers. The quote from the shareholder letter refers to Supercharger locations. Different things. Either way they are way, way behind. I don't see how they can achieve what they said they would.
Yes, they've been pretty careful to use those two different terms at different times when talking about building out the network, listing the global count of Superchargers and Supercharger locations.
 
According to Blueshift, today, Friday July 14, there are 25 SC sites under construction and another 13 in various stages of permitting here in the US. It is quite likely that these will all be up and operational by year end, bringing the total to 375+25+13, or 413.

It is anyone's guess how feverish the construction pace will be once these sites are complete. But I would be surprised if we reach 450 in the next five and one-half months. Hope I am wrong.