The longest EV charging network in West Australia

This site may earn commission on affiliate links.
Jurien Bay civil works are also nearly complete - site is still awaiting Western Power to install the transformer. I took a photo of it and created the site as "Coming Soon" on Plugshare.

1682147435801.png
 
Williams, WA EV Network (see the OpenChargeMap Williams pin for location):

OCM-257192.medi.2023042110060252.jpg



Drive through design.

OCM-257192.medi.2023042110014495.jpg


One 150 kW cabinet and one 7kW post in a drive through configuration.

OCM-257192.medi.2023042110085530.jpg


Charging instructions.

OCM-257192.medi.2023042110095694.jpg


Kempower DC Charger.

OCM-257192.medi.2023042110113917.jpg


7kW AC charger.

OCM-257192.medi.2023042110143198.jpg


Waiting for the transformer to be installed.

OCM-257192.medi.2023042405203503.jpg


Utility cabinet internal.

OCM-257192.medi.2023042405213519.jpg


Kempower DC charger internal.

OCM-257192.medi.2023042405224671.jpg


Location of the soon to be installed credit card post.
 
Lancelin, WA EV Network (see OpenChargeMap Lancelin pin for location):

OCM-202090.medi.2023042505174715.jpg


Site overview. The layout follows the standard pattern for single DC cabinet sites. The credit card post is still to be installed.

OCM-202090.medi.2023042505193779.jpg


7kW AC post. Outlet to be installed.

OCM-202090.medi.2023042505214214.jpg


150 kW DC cabinet.

OCM-202090.medi.2023042505230937.jpg


Utility cabinet.
 
Jurien Bay, WA EV Network (see OpenChargeMap Jurien pin for location):

OCM-202092.medi.2023042516010720.jpg


Site overview. Both the transformer and credit card post to be installed. The layout follows the pattern for single DC cabinet sites.

OCM-202092.medi.2023042515571626.jpg


7kW AC post. Outlet to be installed.

OCM-202092.medi.2023042515561653.jpg


150kW DC cabinet.

OCM-202092.medi.2023042515580431.jpg


Utility cabinet. Transformer to be installed behind this cabinet.
 
  • Like
Reactions: Hairyman and cafz
Good news at Williams, WA. The installation of the transformer is in progress.

The credit card post is still missing.

20230505_161059.jpg


Waiting for hook up to the utility cabinet.

20230505_161134.jpg


Transformer

20230505_161151.jpg



Transformer

20230505_161210.jpg


Transformer

20230505_161230.jpg


I'm waiting patiently for the install to finish so that I can start charging. :)
 
  • Like
Reactions: cafz and Hairyman
Not for another three months o_O, according to the update on last night's TOCWA AUA.

Time to start agitating the Energy Minister to get WP to pull their finger out...

I believe that the same teams of contractors are doing Lancelin, Jurien and Williams. Given that the transformer at Williams is going in right now tose other locations may not be far behind.

I don't drive up that way too often. I would be great if somebody who was driving by could keep us updated.