Background:
We are building a new house. Instead of having a large attached garage w/ my shop/studio above we're doing a small attached garage and then a separate building with the other half of the garage and my shop/studio above that. This is better for our neighbors not having to have a large garage next to their yard and has other benefits (construction costs not one of those benefits).
Original plan was Tesla shingles on both but with the continued delays we're now looking at Tesla shingles only on the studio since the main structure needs a dry roof by mid November. From a power standpoint we'd planned to feed 600a to the studio building and then 400a from there to the main house. This would be quite straightforward for integrating solar, power walls, backup generator, etc.
Our power company, Xcel energy, had agreed to this but then changed their mind. Normally they provide power at the meter but are now saying that they'll not do that for over 400a service and that for 600a they'll provide only a 13.8kV tap at the pole and then we'd be responsible for trenching from the pole to our building, installing a transformer, etc.
So, we're back to square one with 400a to our house, a separate 200a to the studio and possibly another 200a TOU drop to our house for chargers.
The studio will frequently not make use of the power generated by the rooftop solar. One option, since we have net metering, is to just feed it back to the grid.
Question 1: I don't know for how long we'll have net metering though so want to at least be prepared for being able to feed solar generation to our main house if not do it now. Thoughts on how best to do that?
Question 2: We may install a backup generator (Powerwall's would be much too expensive at this point I think though holding off until we see what happens with prices) and the plan was for this to be by the studio which would be fine with the single 600a feed + 400a sub but may be complicated w/ separate feeds? Also not sure about code for tying stuff together on our side of two different meters (I assume all meters will be off the same transformer).
Any other advice very welcomed.
Thanks,
We are building a new house. Instead of having a large attached garage w/ my shop/studio above we're doing a small attached garage and then a separate building with the other half of the garage and my shop/studio above that. This is better for our neighbors not having to have a large garage next to their yard and has other benefits (construction costs not one of those benefits).
Original plan was Tesla shingles on both but with the continued delays we're now looking at Tesla shingles only on the studio since the main structure needs a dry roof by mid November. From a power standpoint we'd planned to feed 600a to the studio building and then 400a from there to the main house. This would be quite straightforward for integrating solar, power walls, backup generator, etc.
Our power company, Xcel energy, had agreed to this but then changed their mind. Normally they provide power at the meter but are now saying that they'll not do that for over 400a service and that for 600a they'll provide only a 13.8kV tap at the pole and then we'd be responsible for trenching from the pole to our building, installing a transformer, etc.
So, we're back to square one with 400a to our house, a separate 200a to the studio and possibly another 200a TOU drop to our house for chargers.
The studio will frequently not make use of the power generated by the rooftop solar. One option, since we have net metering, is to just feed it back to the grid.
Question 1: I don't know for how long we'll have net metering though so want to at least be prepared for being able to feed solar generation to our main house if not do it now. Thoughts on how best to do that?
Question 2: We may install a backup generator (Powerwall's would be much too expensive at this point I think though holding off until we see what happens with prices) and the plan was for this to be by the studio which would be fine with the single 600a feed + 400a sub but may be complicated w/ separate feeds? Also not sure about code for tying stuff together on our side of two different meters (I assume all meters will be off the same transformer).
Any other advice very welcomed.
Thanks,