Welcome to Tesla Motors Club
Discuss Tesla's Model S, Model 3, Model X, Model Y, Cybertruck, Roadster and More.
Register

Wiki UK and Ireland Supercharger Site News

This site may earn commission on affiliate links.
Some pictures of the rumoured Tesla Supercharger spot in Aberystwyth outside the Park Lodge Hotel. I'm not sure if this is how they're meant to look... it certainly doesn't look like there could be 8 of these things here??
PXL_20210523_160413008.jpg
PXL_20210523_160407406.jpg

PXL_20210523_160424922.jpg
 
  • Like
Reactions: PB1975
Some pictures of the rumoured Tesla Supercharger spot in Aberystwyth outside the Park Lodge Hotel. I'm not sure if this is how they're meant to look... it certainly doesn't look like there could be 8 of these things here??
Agree with CMc1, these look like foundations for the power supply (?transformer and other non-Tesla-specific kit). Quite similar to foundations built at other recently opened superchargers (e.g. compare with 2nd and 3rd picture in this post from when Adderstone was under construction). I don't see anything that looks like the square bases & cable holes for the Tesla charging cabinet(s) (or supercharger tombstones) so not possible to infer how many stalls are going in yet, but exciting to see progress underway.
 
  • Like
Reactions: CMc1 and PB1975
Agree with CMc1, these look like foundations for the power supply (?transformer and other non-Tesla-specific kit). Quite similar to foundations built at other recently opened superchargers (e.g. compare with 2nd and 3rd picture in this post from when Adderstone was under construction). I don't see anything that looks like the square bases & cable holes for the Tesla charging cabinet(s) (or supercharger tombstones) so not possible to infer how many stalls are going in yet, but exciting to see progress underway.
My bet would be that these are the non-Tesla cabinet bases (substation and Actenium/other unit) possibly being installed by contractors for the DNO, then Tesla contractors will arrive to install the downstream Tesla hardware.
Fun fact: the concrete bases for the Tesla tombstones are named “square ponies”… they have a label on with that name when they’re delivered.
 
  • Like
Reactions: cezdoc
Ofgem have today officially given the green light for additional funding / support for “green” initiatives, which include upgrading many MSAs (1800 ultra-rapid stalls) to support EVs. Whilst Tesla aren’t mentioned by name, some of the sites are known Tesla SuC sites (present and future) and there could be a few more potential sites included. A few current site may also see upgrades.

This includes power to Woodall and Whetherby as tipped off a few posts ago - supporting the theory these sites are going ahead.

I’ve put some of the EV MSA quotes in below. Main document can be found.


• North Carlisle area strategic reinforcement (£1.4m): delivery of 8km 11kV circuit with associated new switchgear to resolve network constraints to permit the connection of more low carbon technology (LCT) connections, including EV charging at Todhills Services MSA, and provide an interconnection between different parts of the local network to increase resilience for existing customers.

• Lancaster Forton area strategic reinforcement (£0.54m): delivery of 5km 11kV circuit to increase capacity for proposed developments of low carbon technology connections, including EV charging stations at the key M6 Lancaster MSA. Future proofing of investment to facilitate the future upgrade and provide a more enduring solution for accommodating future demand increases.

• Heywood Birch area strategic reinforcement (£0.7m): laying 2 x 4km cables to increase network capacity and help facilitate new connections, including EV charging at Birch MSA and future low carbon technologies around Birch Business Park.

• Durham junction (£3m): new substation to create additional capacity for demand and generation. The project specifically targets the future demand projections of Project Rapid for the local MSA.

• Washington junction (£1.3m): new substation to create additional capacity for demand and generation. The project specifically targets the future demand projections of Project Rapid for the local MSA

• Woodhall junction (£7.3m): investment to support new 66kV feeders energised at HV level to create additional capacity for demand and generation. Proposal considered to deliver a scalable connection for the MSA with the highest projected demand requirements from Project Rapid in the NPg region. Investment will enable the full future demand to be realised later. NPg expect additional asset utilisation to be achieved via large scale distributed generation operators.

• Wetherby junction (£27.0m): investment to support ~30MVA to the MSA and help to unlock a significant amount of renewable generation and development potential in Wetherby alongside providing a range of other system synergies.

• Phase 1 Tatton New MSA (£0.59m): installation of new substation to support EV charging requirements at a planned Motorway Service station at Tatton.

• Poplar MSA, M6 Junction 20 / M56 Junction 9 (£2.44m): installation and commission of a new 33/11kV double primary substation at the Poplar 2000 Lymm MSA initially supporting the demand for essential EV services.

• Knutsford MSA, M6 Junction 19 Northbound & Southbound (£2.58m): installation of new 33/11kV double primary substation site with ancillary equipment. This requires the installation of approximately 2.2km double circuit 33kV underground cable.

• Sandbach MSA, M6 Junction 17 Northbound & Southbound (£2.05m): installation of a new 33/11kV double primary substation site, comprising two 33/11kV 10MVA transformers, corresponding 33kV and 11kV switchgear and all ancillary equipment and two 33kV cable circuits.

• Hapsford MSA, M56 Junction 14 (£1.79m): installation of a new 33/11kV double primary substation site, comprising two 33/11kV 10MVA transformers, corresponding 33kV and 11kV switchgear and all ancillary equipment. This requires the installation of approximately 0.6km double circuit 33kV underground cable with association equipment.

• Burtonwood Services MSA, M62 Junction 8 Eastbound (£2.14m): installation and commission of a new double primary substation at Burtonwood MSA, supporting the demand for essential EV services.

• Wheatley (£3.9m): investment to enable the reinforcement of the Wheatley transformers and OHL between Wheatley, Headington and Cowley, providing 14MW of additional capacity. 8.58MW of this capacity will support general domestic LCT uptake in the area as well as the significant growth in EV charging requirements at the Oxford motorway service area.

• Rownhams - North Southampton (£9.6m): reinforcement of Rownhams substation and the installation of two 33kV new cables from Rownhams substation to a new substation at Rownhams MSA, creating 30MW of additional capacity. SSEN believe that scheme proposes a long-term, whole system optimised solution at both the north and south sides of Rownhams MSA.

• Category 1 (7 sites proposed for immediate delivery): investment of £20.9m to deliver 56MVA of capacity, equivalent to 750 ultra-rapid chargers, providing 100 miles of range within 10 mins of charge. All proposed circuits would be installed in 33kV construction and connected at 11kV in the short term to provide optionality for greater capacity in the future as required (post 2030). The sites covered include Baldock, Peterborough, London Gateway, Thurrock, Cobham, Pease Pottage and Cambridge.

• Category 2 (3 sites): investment of an additional £20.9m (at higher unit cost) to deliver 48MVA of capacity, equivalent to 640 ultra-rapid chargers within RIIO-ED1. Installation of all circuits in 33kV construction and to connect at 11kV in the short- term as per Category 1. The three sites covered Toddington, South Mimms and Medway.

• Category 3 (3 sites) – investment of £23m to deliver 24 MVA of capacity, equivalent to 320 ultra-rapid chargers at 3 additional sites – Birchanger, Clackett Lane and Maidstone. These additional sites were identified as options that UKPN could progress under Green Recovery dependent on an Ofgem review of whole system value, including transmission alternatives. Alternatively, UKPN identified that the proposals could be delivered under the RIIO-ED2 price control starting in 2023 and subject to the standard determination process for these controls.

• WPD’s submission includes 15 MSA or trunk road EV charging related proposals. These include:

• Tamworth MSA, East Midlands (£1.87m): new 33kV connection at a 33- metering substation and associated works, facilitating the release of 18MW of additional demand capacity. Supports MSA rapid charging and potential connection of further renewable generation and other LCT connections.

• Northampton MSA, East Midlands (£0.75m): upgrade to 11kV connection at 2 metered substations, each served by new RMUs, fed directly from Banbury Lane Primary. Installation of 1500m of 11kV cable across two circuits to connect to the nearby Primary and two new 11kV circuit breakers at the Primary with potential need to extend the building if other connections in area proceed.

• Cardiff Gate MSA, M4, South Wales (£1.4m): extension of the existing 11kV switchboard at St Mellons Primary Substation with two new feeder circuit breakers and installation of 2 x 2.5km 11kV underground, releasing 8MW of demand capacity. Supports MSA rapid charging and potential connection of further renewable generation and other LCT connections

• Magor, M4 MSA, South Wales (£1.3m): replacement of the 11kV switchboard at Magor BSP and associated works to accommodate two new 11kV circuit breakers, to provide supplies to Magor MSA. Expected to support 8MW of additional demand capacity for MSA rapid charging and the connection of further renewable generation.

• Pont Abraham MSA, South West (£1.8m): installation of 2 x 5000m 11kV cables to location within Pont Abraham MSA with associated infrastructure upgrades. Expected to release 8MW of additional demand capacity to serve the MSA with infrastructure able to connect potential further renewable generation within limits of existing 33kV network.

• Gordano, M5 MSA, South West (£1.7m): installation of new cables (~1.5km) in single cable sections and unbundle with new 33kV equipment to form a 33kV ring, new 33kV switch room and 33kV cable to connect to MSA through a new 33/11kV primary substation.

• Frankley North & South M5 MSA, West Midlands (£1.5m): installation of two new 11KV circuit breakers installed at Bartley Green BSP, with 2 x 3.6km HV cables installed from the BSP to the MSA site. A new 11KV metered substation is to be installed onsite to provide the connection.

• Gloucester Services MSA, West Midlands (£1.6m): installation of two new 11kV Cu cable circuits and associated network infrastructure, including installation of two 11kV circuit breakers at Gloucester Services in a building provided by the customer. Project expected to release 8MW of additional demand capacity, primarily for rapid EV charging at Gloucester Services with some scope for further renewable generation and LCT demand growth on south side of Gloucester.

• Hopwood Park, M42 MSA, West Midlands (£2.0m): installation two new 11KV circuit breakers at Longbridge 132/11 BSP with two new HV cables installed from the BSP to the MSA site. A new 11KV metered substation is to be installed onsite to provide the 8MW connection. Project expected to release 1-2MW of capacity initially with potential for further support to connections of additional renewable generation.

• Michaelwood, M5 MSA, West Midlands (£2.4m): extending the existing 11kV switch board to provide 2 x feeder breakers and lay 2 x 4.7 km cables to the north and south bound MSAs and install with associated infrastructure upgrades. This infrastructure releases 8MW of demand capacity to the site, which will also be available to support further renewable generation.

• Norton Cannes, M6 Toll MSA, West Midlands (£1.5m): installation of two new 11KV circuit breakers installed at Burntwood 132/11kV BSP and two 4km HV cables from the BSP to the MSA site. A new 11KV metered substation is to be installed onsite to provide the 8MW connection. The project is expected to provide 8MW of additional demand capacity for rapid EV charging at the MSA as well as capacity to connect further renewable generation and other LCT demand.

• Tibshelf Northbound, East Midlands (£5.6m): installation of two additional 33kV circuit breakers and two 33kV cable circuits from Alfreton BSP to Tibshelf Northbound Services Station. Supported by installation of 33kV equipment and transformation on site and replacement of both 132/33kV transformers with 90MVA units, including associated 33kV cables. Investment expected to release 27MW demand capacity.

• Watford Gap, East Midlands (£0.2m): Upgrade to an 11kV connection at 2 metered substations, each served by new RMUs. 200m of 11kV cable is required to make the connection. 8MW of demand released to support the MSA and potential renewable generation connections

• New BSP at Bridgwater, South West (£4.25m): scheme will establish a new 2 x transformer 132/33kV BSP near Bridgwater GSP with associated infrastructure works. The new grid transformers will feed a new 33kV switchboard from which the new Gravity Project connection and other customers (the Gravity Project is expected to fund the costs of the 33kV cable to their site and the required 33/11kV assets). The new BSP will provide up to 90MVA additional demand headroom (114MVA cyclic) of which 40MVA would be used by Gravity. The new BSP is also expected to create 60MVA of generation headroom.

• Hammerley Down 33kV Reinforcement, West Midlands (£3.9m): installation of a further 33kV circuit and create a two-switch mesh at Hammerley Down with an outgoing circuit to Alveston. Upgrades expected to release 15MW of additional capacity will be released, supporting rapid EV charging at local service station and potential connection of further renewable generation and LCT demand.
 
Ofgem have today officially given the green light for additional funding / support for “green” initiatives, which include upgrading many MSAs (1800 ultra-rapid stalls) to support EVs. Whilst Tesla aren’t mentioned by name, some of the sites are known Tesla SuC sites (present and future) and there could be a few more potential sites included. A few current site may also see upgrades.

This includes power to Woodall and Whetherby as tipped off a few posts ago - supporting the theory these sites are going ahead.

I’ve put some of the EV MSA quotes in below. Main document can be found.

Brilliant stuff. Only questions timescales but it’s excellent to see such forward planning and commitment. It seems comprehensive too with sites at the extremities of the network such as Pont Abraham specified too.
 
  • Like
Reactions: Godsense and CMc1
Ofgem have today officially given the green light for additional funding / support for “green” initiatives, which include upgrading many MSAs (1800 ultra-rapid stalls) to support EVs. Whilst Tesla aren’t mentioned by name, some of the sites are known Tesla SuC sites (present and future) and there could be a few more potential sites included. A few current site may also see upgrades.

This includes power to Woodall and Whetherby as tipped off a few posts ago - supporting the theory these sites are going ahead.

I’ve put some of the EV MSA quotes in below. Main document can be found.

Are you suggesting Woodall North will actually be completed or are we talking a southbound upgrade. Either of both of which would be most welcome
 
  • Like
Reactions: adsheff
Are you suggesting Woodall North will actually be completed or are we talking a southbound upgrade. Either of both of which would be most welcome
Everything points at Woodall North going ahead later in the year - with power supply upgrade work by the DNO starting starting late autumn.

Southbound upgrade could be a a side project as a result of the upcoming power supply upgrade. But no evidence. Purely speculative.
 
  • Like
Reactions: adsheff
Tell me about it. Just one supercharger in the whole of kent (Maidstone).

Can forget the one at Folkestone as it's post check in at the Eurotunnel, i.e completely inaccessible unless you are travelling to France
Yep, it's really not great in Kent and East Sussex. There's some at Bluewater, but Sevenoaks likely won't be available till end of the year. I've often wondered why there was never any desire to put some in Canterbury or Ashford given the demand.
 
Yep, it's really not great in Kent and East Sussex. There's some at Bluewater, but Sevenoaks likely won't be available till end of the year. I've often wondered why there was never any desire to put some in Canterbury or Ashford given the demand.
I drove down to Deal from North London and although there is Maidstone SC half-way there is only one 7Kw charger in Asda in Deal. I arrived home with 5% battery having left that morning on 100%.
 
This includes power to Woodall and Whetherby as tipped off a few posts ago - supporting the theory these sites are going ahead.

However, reading the document you linked, Woodall got approved but the proposal for Wetherby was not accepted for this round (or at least, 'Wetherby phase 1' was accepted, but 'phase 2' - the actual cable to the MSA and associated substation - was not).
 
  • Helpful
Reactions: CMc1
Tell me about it. Just one supercharger in the whole of kent (Maidstone).

Can forget the one at Folkestone as it's post check in at the Eurotunnel, i.e completely inaccessible unless you are travelling to France.
The InstaVolt x 2 at Bannatynes Gym in Broadstairs is a useful Kent location if you’re spending time down the far end of Kent around the Margate Région. Obviously this thread is about Superchargers but in the absence of anything else, it’s a good get out of jail free option and I’ve used it a few times.
 
  • Like
Reactions: AnthonyLR
Anyone have any details of the Sevenoaks Supercharger? The Southern M25 is a bit of a desert...
Not yet. Clackett Lane could be thought of as ‘Sevenoaks’ at a stretch, and considering it was listed on the Tesla website at the same time as Rownhams then that could make sense. Rownhams was the first Roadchef Supercharger site to be uncovered, and therefore the Clackett Lane Roadchef is a distinct possibility.
if it isn’t there then it may be just south of the M25 where there is both decent HV supply and a number of pieces of land that are viable.
With the amount of investment in HPCs at service areas this year, my money is on Clackett Lance. 🤞🏼