Welcome to Tesla Motors Club
Discuss Tesla's Model S, Model 3, Model X, Model Y, Cybertruck, Roadster and More.
Register

Search results

  1. Z

    Supercharger - Chemult, OR - US-97 (under construction April 2024, 8 V3 stalls)

    That definitely looks like the transformer! Hopefully close to going online!
  2. Z

    Supercharger - Weed, CA (LIVE 17 May 2024, 16 V4 stalls)

    Has anyone driven past this one recently, or have plans to go through and check it out?
  3. Z

    Supercharger - Pollock Pines, CA (LIVE 18 Jan 2024, 12 V3 stalls)

    I believe the two other spots will be ADA and will be located in the red area below. The other 10 from your pictures are located in the blue area.
  4. Z

    Supercharger - Anderson, CA (LIVE 28 Mar 2024, 8 V3 stalls)

    That would be my guess. The approved plans show the transformer being placed behind the cabinets on a concrete pad that hasn't been placed/constructed yet. Hopefully when they did the concrete pad for the cabinets, they stubbed out the necessary conduit and capped it to tie into the...
  5. Z

    Supercharger - El Dorado Hills, CA (LIVE 6 Oct 2023, 12 V3 stalls)

    Checked the site this morning and the transformer has been installed. There is still quite a bit of pavement restoration to be done where they trenched from the transformer pad to the cabinets. Once that's done, I'm guessing it won't be long before it's turned on.
  6. Z

    Supercharger - El Dorado Hills, CA (LIVE 6 Oct 2023, 12 V3 stalls)

    Looks like work to install the transformer pad behind Bark Avenue has started, and trenching work to connect the transformer to the cabinets in the parking lot is starting today.
  7. Z

    Supercharger - El Dorado Hills, CA (LIVE 6 Oct 2023, 12 V3 stalls)

    Not quite accurate. The site is completed, all pedestals and cabinets installed, repaving and parking lot striping completed. Just waiting on transformer installation. This site is a bit different in that the transformer is being installed a couple hundred feet away from the cabinets and...
  8. Z

    Supercharger - Pollock Pines, CA (LIVE 18 Jan 2024, 12 V3 stalls)

    Looks like this one is under construction. @Chuq @corywright @bmah
  9. Z

    Supercharger - South Lake Tahoe, CA (LIVE 21 Nov 2023, 8 V3 stalls)

    Permit was issued on 5/12/2023, so hopefully getting ready to break ground.
  10. Z

    Supercharger - Bend, OR - SW. Industrial Way (LIVE Jun 2023, 8 V3 stalls)

    Drove by to check just now and was able to plug in and charge. Tesla employee was still onsite and said it had only been live for an hour and should show up on the app in the next 24-48 hours. Charging at reduced rate but he said it will pick up once it goes live on the app and in-car
  11. Z

    Supercharger - Bend, OR - SW. Industrial Way (LIVE Jun 2023, 8 V3 stalls)

    Anyone been by this one in the past couple of weeks? Headed up to Sunriver next week from the Sacramento area with a roof box on top of the Model Y. A little anxious to see what that does to our range. It would be great to have a V3 supercharger in Bend to speed up the charging.
  12. Z

    Supercharger - Anderson, CA (LIVE 28 Mar 2024, 8 V3 stalls)

    Any update on this one in the past few weeks? Headed up to Sunriver next week from the Sacramento area with a roof box on top of the Model Y. A little anxious to see what that does to our range and would be nice to have another option along the way.
  13. Z

    Road Trip to Sunriver, Oregon this Summer

    Thanks for the responses. I've got family in K-Falls, so we'll be spending a night or two there on the way up. Sounds like we'll head straight from K-Falls to the Bend supercharger to start the week off with a full-ish charge in Sunriver.
  14. Z

    Road Trip to Sunriver, Oregon this Summer

    My family and I are headed to Sunriver for a week this summer (last stop before Sunriver will be the supercharger in Klamath Falls) and it looks like the charging options are pretty limited once we get there. I know Bend has a supercharger and another under construction right now, but that's...
  15. Z

    Supercharger - Cameron Park, CA (LIVE 12 May 2023, 12 stalls)

    Looks like the Tesla permit has been "Finaled." Just waiting for the Moonraker project to wrap up before opening I would guess.
  16. Z

    Supercharger - Castaic, CA (LIVE 13 Aug 2022, 12 V3 stalls)

    Building permit still not issued as of today, 4/1.
  17. Z

    Supercharger - Placerville, CA (Missouri Flat Rd., LIVE 15 May 2021, 8 V3 stalls + Magic Docks)

    This one is showing up on the in-car nav this morning. Looks like this one (finally) got turned on.
  18. Z

    Supercharger - Placerville, CA (Missouri Flat Rd., LIVE 15 May 2021, 8 V3 stalls + Magic Docks)

    I went by yesterday around lunchtime and the PG&E has been installed within the enclosure. The other trenching work in the Target parking lot I mentioned in my post above appears to be for new landscape irrigation rather than additional chargers. All the pedestals were still wrapped up in the...
  19. Z

    Supercharger - Placerville, CA (Missouri Flat Rd., LIVE 15 May 2021, 8 V3 stalls + Magic Docks)

    Some activity has been going on recently. It looks as if they may be trenching from the cabinet enclosure for some additional EV chargers out in the middle of the Target parking lot. A section of the enclosure wall has been removed (nearest the transformer pad). Although this is strange...
  20. Z

    Supercharger - Placerville, CA (Missouri Flat Rd., LIVE 15 May 2021, 8 V3 stalls + Magic Docks)

    Still waiting on PG&E transformer at this location as of this morning.
  21. Z

    Supercharger - Placerville, CA (Missouri Flat Rd., LIVE 15 May 2021, 8 V3 stalls + Magic Docks)

    Took this photo yesterday. Looks like we're still waiting on the transformer from PG&E. Not sure what the other set of conduits sticking up are for. Future expansion maybe?
  22. Z

    Supercharger - Placerville, CA (Missouri Flat Rd., LIVE 15 May 2021, 8 V3 stalls + Magic Docks)

    Fencing is all down. They've reinstalled all the cabinets and pulled all the wires. Striping is down for all the parking stalls and the site looks 100% complete. Only thing missing is the PG&E transformer.
  23. Z

    Supercharger - Placerville, CA (Missouri Flat Rd., LIVE 15 May 2021, 8 V3 stalls + Magic Docks)

    Progress seems to have hit a snag. I went by yesterday and they had removed the metal enclsoure/fencing from around the cabinets, removed all the cabinets, and were jackhammering out the concrete pad. There must be some issue with the conduit under the pad. Looks like a fairly significant...
  24. Z

    Supercharger - Placerville, CA (Missouri Flat Rd., LIVE 15 May 2021, 8 V3 stalls + Magic Docks)

    Looked like the chain link fence was back up and a crew was there working this afternoon. It looked like they were removing one of the cabinets from the enclosure. Still waiting on a transformer inside the fenced off enclosure too it looked like.
  25. Z

    Supercharger - Placerville, CA (Missouri Flat Rd., LIVE 15 May 2021, 8 V3 stalls + Magic Docks)

    This is in the parking lot of a new Target that is due to open soon (converted from the old K-Mart). Great find!
  26. Z

    Supercharger - Folsom, CA - Palladio Parkway (LIVE 11 Aug 2016, 10 V2 + 20 V3 stalls)

    Drove through the parking garage tonight and saw a van there with a guy working on the new pedestals. About half of them were lit up and there appeared to be a car charging. My wife was in a hurry so I couldn't stop to plug in.
  27. Z

    Supercharger - Folsom, CA - Palladio Parkway (LIVE 11 Aug 2016, 10 V2 + 20 V3 stalls)

    Looks completed now. All construction equipment and debris is gone. New pedestals are just wrapped in caution tape.
  28. Z

    Supercharger - Folsom, CA - Palladio Parkway (LIVE 11 Aug 2016, 10 V2 + 20 V3 stalls)

    Went by this morning and the fence has been taken down. Looks like just site cleanup left to finish up. Hopefully online in the next week or two. Also counted 20 V3 pedestals waiting to go online.
  29. Z

    Supercharger - Folsom, CA - Palladio Parkway (LIVE 11 Aug 2016, 10 V2 + 20 V3 stalls)

    I believe there are 5 V3 cabinets, which could potentially be an additional 20 V3 stalls at this location, in addition to the existing 10 V2 stalls.
  30. Z

    Supercharger - Folsom, CA - Palladio Parkway (LIVE 11 Aug 2016, 10 V2 + 20 V3 stalls)

    I drove through yesterday afternoon and it looks like all 5 cabinets and all the pedestals have been installed. All conduit runs look just about finished. Even the parking stops have been installed. Work still progressing even with all the restrictions right now. Hopefully wrapping up soon.
  31. Z

    Supercharger - Folsom, CA - Palladio Parkway (LIVE 11 Aug 2016, 10 V2 + 20 V3 stalls)

    Lots of conduit going in where cabinets will be installed.
  32. Z

    Supercharger - Folsom, CA - Palladio Parkway (LIVE 11 Aug 2016, 10 V2 + 20 V3 stalls)

    It looks like there are 4 cabinets and one other piece of slightly larger sized equipment. I counted 24 parking spaces fenced off, but I'm sure some of those are just for room for equipment and materials during construction. At least one space is being taken up for the cabinets themselves.
  33. Z

    Supercharger - Roseville, CA - Galleria Boulevard (LIVE 21 Feb 2020, 20 V2 stalls)

    Should have added that all the fencing is down as well. Here are a few photos I took.
  34. Z

    Supercharger - Roseville, CA - Galleria Boulevard (LIVE 21 Feb 2020, 20 V2 stalls)

    Went by this morning to check on progress. All paving and pavement markings have been completed. Looks like the pad for the transformer has been formed up but no concrete yet. All Tesla signs are up for each stall. No sign of urban pedestals yet either.