Welcome to Tesla Motors Club
Discuss Tesla's Model S, Model 3, Model X, Model Y, Cybertruck, Roadster and More.
Register

Search results

  1. STDRDC13

    Supercharger - Houston, TX - Queensbury Lane (CITYCENTRE)

    Zero progress on the equipment pads for transformer and switchgear since post #16 on Dec. 15, 2023.
  2. STDRDC13

    Supercharger - Houston, TX - Queensbury Lane (CITYCENTRE)

    I believe the site is in need of a transformer. I pass by there today and will see about getting a few pics.
  3. STDRDC13

    Supercharger - Waxahachie, TX

    The reason I've found for the delay is the site work has to pass inspections before the utility company will release the transformer to be set, and those pad mount transformers are not always sitting in stock. It's not uncommon for SC sites wait months for the transformer to arrive. Its now just...
  4. STDRDC13

    Supercharger - Houston, TX - Washington Avenue

    Transformer and Switchgear pads poured and awaiting the equipment placement.
  5. STDRDC13

    Supercharger - Houston, TX - Washington Avenue

    This is the first time I’ve seen V4’s in Houston Transformer and Switchgear equip pads formed but not poured.
  6. STDRDC13

    Supercharger - New Caney, TX

    Drove by last night and noticed the 4 pedestals on the PSU closest to Kroger were not illuminated...so 12 of 16 live.
  7. STDRDC13

    Supercharger - New Caney, TX

    They are powered up @Guacahummus @Cory
  8. STDRDC13

    Supercharger - New Caney, TX

    They are powered up @Guacahummus @corywright
  9. STDRDC13

    Supercharger - New Caney, TX

    Transformer and meter installed Meter display is blank indicating no power to transformer yet,
  10. STDRDC13

    Supercharger - New Caney, TX

    Again...no Transformer as of 12.26.2023.
  11. STDRDC13

    Supercharger - New Caney, TX

    No X-former as of 12.1.2023
  12. STDRDC13

    Supercharger - New Caney, TX

    No X-former as of 11.16.2023
  13. STDRDC13

    Supercharger - Humble, TX

    Definitely online as 2 3’s were charging @Guacahummus
  14. STDRDC13

    Supercharger - New Caney, TX

    The tap box has been set and now the transformer is the device to keep an eye out for its arrival.
  15. STDRDC13

    Supercharger - Humble, TX

    The fuses are in place and meter set and displaying a read out. Just waiting on Tesla at this point. I did notice that the level two chargers are a mix of 1772 (the black ones) and NACS (the white ones)
  16. STDRDC13

    Supercharger - Humble, TX

    Did you notice if the fuses at the overhead connection were in place? If they were the meter is likely set as well and just waiting for Tesla to come out and commission the site.
  17. STDRDC13

    Supercharger - Luling, TX

    @Guacahummus @corywright
  18. STDRDC13

    Supercharger - Converse, TX

    I'm gonna guess since the transformer bank you are referring to is (a) already in use due to the fuses in place and (b) only 300kVa (3-100's), that these chargers will receive power from a new and much larger service. If Guacahummus can find some drawings we can certainly tell if its a pad or...
  19. STDRDC13

    Supercharger - Humble, TX

    Still Hanging as of Halloween Eve '23
  20. STDRDC13

    Supercharger - Luling, TX

    How's the Supercharger construction going?
  21. STDRDC13

    Supercharger - New Caney, TX

    You'll have the drive up to DFW to find the 1 and only (i believe) Tx Magic Dock.
  22. STDRDC13

    Supercharger - Humble, TX

    Main feeders still hanging as seen in Post #31
  23. STDRDC13

    Supercharger - Houston, TX - West Alabama Street (PERMANENTLY CLOSED)

    Picture taken by a friend shows charging pedestals bagged.
  24. STDRDC13

    Supercharger - Humble, TX

    Drove by Saturday and most of the site clean up has been completed with just a few palatized wire spools to be picked up. Construction fence has been taken down and removed. Guessing an inspection is hanging out there?
  25. STDRDC13

    Supercharger - Vernon, TX

    I wonder if you could charge using your mobile with the NEMA 14-50 at the new'ish RV Park? At least enough to get you to a SC.
  26. STDRDC13

    Supercharger - Houston, TX - Kipling Street

    The entrance has been completed and transformer installed…sparky is onsite along with CofH inspector which will hopefully give utility company the green light to energize the transformer.
  27. STDRDC13

    Supercharger - Humble, TX

    Main feeders are still hanging from the weather heads awaiting the utility company to connect to the overhead transformers.
  28. STDRDC13

    Supercharger - Houston, TX - Kipling Street

    Entrance looks ready for concrete.
  29. STDRDC13

    Supercharger - Pearland, TX

    Utility power is hooked up and meter has been installed along with the fuses. It appeared that Tesla commissioning agents were on site
  30. STDRDC13

    Supercharger - New Caney, TX

    Are non-Tesla EVs being allowed to charge at non Magic Dock locations? I know we can't visually identify these chargers as Magic Docks due to the protective shipping material they are wrapped in currently, but that would be interesting to know. I don't believe I've seen a mix of "standard NACS"...
  31. STDRDC13

    Supercharger - New Caney, TX

    The “4-bangers” have arrived.
  32. STDRDC13

    Supercharger - Houston, TX - Kipling Street

    Entrance still remains unfinished, but there was a new pile of rocks just feet away?
  33. STDRDC13

    Supercharger - Humble, TX

    The contractors onsite will run the feeder wires (shown hanging in post #31) to each of the utility poles and leave them hanging out of the weatherheads. Then there will be a final electrical inspection and once the utility company (CenterPoint) sees a PASSED, they will come out and make the...
  34. STDRDC13

    Supercharger - New Caney, TX

    No PSU’s onsite yet, but the tap box and transformer pads are being formed up currently.
  35. STDRDC13

    Supercharger - Humble, TX

    Once the contractor gets these “house lines” installed and inspected, CenterPoint will come out and make the connections, install the fuses, set the meter. Then Tesla commissioning.
  36. STDRDC13

    Supercharger - New Caney, TX

    Trench backfill and compaction is complete… Ready for the prefab’s to be set.
  37. STDRDC13

    Supercharger - New Caney, TX

    Location of the prefab install boxed.
  38. STDRDC13

    Supercharger - New Caney, TX

    @rstx AFIRM...!!! And you can see evidence of the pop-up car meets I mentioned in an earlier post.
  39. STDRDC13

    Supercharger - New Caney, TX

    Based on the orientation of the conduit ran, it appears there will be 4 prefabs used at this site. Tesla equipment will arrive once the site is ready to accept them. So it may be a bit before we see Tesla equipment to change this to a cone.
  40. STDRDC13

    Supercharger - New Caney, TX

    Earth work has begun with a long trench suggesting this project will not utilize the prefab 4-bangers. There is routinely pop-up muscle car shows in this which should an interesting culture clash.
  41. STDRDC13

    Supercharger - Humble, TX

    Site cleanup is underway with the striping complete for the LIII chargers, but not yet complete for the LII. Maybe a final electrical inspection to release utility company to make the connection
  42. STDRDC13

    Supercharger - Pearland, TX

    The equipment pad appears to have been poured and the SC cabinets were being set in place today.
  43. STDRDC13

    Supercharger - Dripping Springs, TX

    Yeah if you ever see the SC cabinets show up with the center of gravity bullseye looking mark on the side, that’s definitely not a PSU or whatever Tesla calls the 4-banger prefabs.
  44. STDRDC13

    Supercharger - Houston, TX - Kipling Street

    Nothing transformer related will take place until the entrance has been poured/paved.
  45. STDRDC13

    Supercharger - Houston, TX - Kipling Street

    I rarely charge away from the house locally, but I have a friend who shops at that HEB and its always a mess with a wait apparently. But I've never charged there and going off hearsay. Either way I agree more chargers the better.
  46. STDRDC13

    Supercharger - Houston, TX - Kipling Street

    Drove by and still an empty transformer pad.
  47. STDRDC13

    Supercharger - Humble, TX

    Tesla equipment pad has been poured and SC cabinets set.
  48. STDRDC13

    Supercharger - Pearland, TX

    Based on the pictures (and the SC Cabinets location) it appears the equipment pad has yet to be poured...they were making great progress, wonder what has slowed them down?
  49. STDRDC13

    Supercharger - Luling, TX

    Any update on the construction side of the Supercharger?