Encouraging news.
Stopped by and s/w the crew today. The work yesterday and today was to remove the 12th charging station and pour a new cement pedestal that is handicap accessible. Expect to finished wiring the new station today. Today they also ran some wiring from the new National Grid pole in the back corner of the parking lot to the supercharger area. However, they are still waiting on the transformer. I asked him if thought the supercharger could be operational within weeks vs. months and he hedged a little but said that is possible. Wild car as always is National Grid but he seemed positive. 1 year anniversary of when they started working on the supercharger location just passed according to him with a laugh. Since I drive by pretty much every day I'll post any updates.