A local needs to find the pad that will hold the transformer (I think it's that concrete pad out on the island). As always, a site needs:
- The pedestals
- The Tesla power distribution cabinets (big and white)
- The transformer (supplied and installed by the electricity company)
- The meter (also provided by the electricity company)
- Meter has power
For this site, items 3 and 4 need to be confirmed or monitored for installation.