You can install our site as a web app on your iOS device by utilizing the Add to Home Screen feature in Safari. Please see this thread for more details on this.
Note: This feature may not be available in some browsers.
The vaults are centered between each set of 8 cabinets. During construction it looked like they dug out for underground transformers.I live in Claremont. This is great. Where are the vaults for the 2 transformers in the pictures ?
Large, need 8 MW each. Does that mean transformers don’t show above ground level ?
A favorable reason for this location is that there is a high voltage spur line that feeds a sub station just to the west on Pomona College campus and it supplies all Claremont College campuses. That HV line should have plenty of capacity for this SC installation.
Each v3 cabinet, supplying 4 charging posts, draws around 350kVA from the grid.I live in Claremont. This is great. Where are the vaults for the 2 transformers in the pictures ?
Large, need 8 MW each. Does that mean transformers don’t show above ground level ?
A favorable reason for this location is that there is a high voltage spur line that feeds a sub station just to the west on Pomona College campus and it supplies all Claremont College campuses. That HV line should have plenty of capacity for this SC installation.
Today Friday May 3 Edison tech was on site, said he was installing the meters. He said transformers would follow “soon”Each v3 cabinet, supplying 4 charging posts, draws around 350kVA from the grid.
So the overall site should need something like 2 x 2800kVA.
They may end up getting two 4000amp 480V feeds from SCE, which would come from the 12kV distribution network.
The 66kV line feeding claremont colleges private substation is certainly a lot of capacity, but probably not something they would end up using.
Transformer is not related to the Tesla team being let go. That is on the utility. There are sites that were/are under construction at the time of the fire that continue being built so it should be no different here. The parking lot painting could be waiting on the transformer installation for some reason. Or some other reason not related to the Tesla team being fired. This should be in the hands of subcontractors.Since they fired the supercharging staff this site stalled. No transformers and they never painted the parking lot.
I agree, just very interesting that the push to complete has stalled. Striping is relatively easyTransformer is not related to the Tesla team being let go. That is on the utility. There are sites that were/are under construction at the time of the fire that continue being built so it should be no different here. The parking lot painting could be waiting on the transformer installation for some reason. Or some other reason not related to the Tesla team being fired. This should be in the hands of subcontractors.
This happens with a lot of sites. They could be months out on the transformer so the striping gets put on back burner for sub contractors.I agree, just very interesting that the push to complete has stalled. Striping is relatively easy
Because there hasn't been activity for 2 weeks? Jeez, lets give it a rest on the "every under construction site is being abandoned" hyperbole. Sites under construction are being finished. There are delays that existed before the team was let go that will continue to be a problem. Transformers being the main one. The main job of the team was planning these sites. Once they were permitted and a contractor was hired, they moved on to PLANNING the next site. If these sites sit for 3 or more months with no movement then we can start to question but I don't see Tesla just walking away from all this INSTALLED equipment when it would only take minimal work with no planning and minimal cost to finish them.True but FWiW, the La Verne site also appears to have been abandoned.
I never said they abandoned. I said they have been affected. I work for one of the largest utilities here in California, I know about delays. It’s most likely a sheer coincidence that all further progress has stopped since the “layoffs”.Because there hasn't been activity for 2 weeks? Jeez, lets give it a rest on the "every under construction site is being abandoned" hyperbole. Sites under construction are being finished. There are delays that existed before the team was let go that will continue to be a problem. Transformers being the main one. The main job of the team was planning these sites. Once they were permitted and a contractor was hired, they moved on to PLANNING the next site. If these sites sit for 3 or more months with no movement then we can start to question but I don't see Tesla just walking away from all this INSTALLED equipment when it would only take minimal work with no planning and minimal cost to finish them.
—————————————————————————————————True but FWiW, the La Verne site also appears to have been abandoned.
Caught! I did use the word abandoned. It’s just interesting that the contractors stopped any forward progress at the same time of the layoffs. Obviously they will finish these sites but now it’s a matter of how long.—————————————————————————————————