RichardV
Member
The Seven Hills BP does not meet the fundings requirements. It is only a single 75 kW unit with two cables. I assume this Seven Hills site was an unfunded site. There is another BP up the road in Seven Hills, where the grant specified, there is no EV charging there. It is possible it was intended to upgrade the single one they put in with a change of venue or that the original site was still their plan. But this is all moot now.Round 1 (2022):
- It should be noted that BP has "pulled the plug" on its sites too. BP won 16 sites with 64 bays, but has built only 1 of them (Seven Hills) the remainder not started.