Well-Known Member
Looks the same as last weeks photos, just that the concrete has dried/cured, I don’t think any additional work has been done.View attachment 1047858
The accessible spot concrete is done. No transformer or additional SC stalls or cabinet installed yet. Site looks like not much is actively happening atm
There won’t be additional stalls at this time. Permit is for 8 with expansion later. The post on the left (2A) will be removed from the PSU and placed onto the conduit stub in the ADA cutout and the stalls will be restriped according to the plans. The right portion of that current middle stall will be an ADA crosswalk coming towards the camera.