  1. J

    Supercharger - Lagrangeville, NY

    Forgot to say, yes all stalls equipped with magic dock CCS adapter see picture above.
  2. J

    Supercharger - Lagrangeville, NY

    Visited today, looks complete except transformer. Transformer pad has remnants of sealing foam so if I had to guess transformer may have failed during installation. Note meter has been installed usually the last step. Utility is Central Hudson G & E. Nice location close to Taconic Parkway...
  3. J

    Supercharger - Brewster, NY

    Thursday 12/22 5:47 just passed by Brewster Supercharger site. All chargers are now lit up. Please note site active on Tesla App. Guys this has been a long wait through many stages, but were are NOW ACTIVE. I suggest a meet up for coffee, any suggestions for a date & time. To all, best of...
  4. J

    Supercharger - Brewster, NY

    Monday evening I talked to a Tesla technician who was working on the site. His model Y was charging and all 8 chargers were lit up. As you know Tesla employees are instructed to give out as little information as possible. I asked about the pole light that was not operating and advise it was...
  5. J

    Supercharger - Brewster, NY

    I drove by at 6:50 tonight and the four stalls were back on. On my earlier trip at 3:20 all were off. Maybe a tech made a visit or there is some remote diagnostic capability. My vote is to not list this site return to service in supercharger.info until things are more stable or someone does a...
  6. J

    Supercharger - Brewster, NY

    All Stalls dark. I just went by at 7:30 tonight, Sorry to say all stalls are dark. Site looks out of service. I am passing by every day so I will post any change in Status.
  7. J

    Supercharger - Brewster, NY

    Technician on-site at 7:00 PM. He has started the commissioning process. I will stop by to confirm charging is active.
  8. J

    Supercharger - Brewster, NY

    Progress continuing today, 8 charge stands mounted and wired. Light pole and fixture set on foundation. The site has concrete paving done. Note sure if there will be a layer of asphalt on top. Note, transformer pad has been poured but no transformer or meter housing seems to be on site...
  9. J

    Supercharger - Brewster, NY

    Update on progress. Two V3 Cabinets were unloaded last night as well as 8 bases and 8 posts. This information was confirmed to me by the power contractor. As of today excavation including retaining walls and curbs as well as a connection to the on-site storm water system were completed...
  10. J

    Supercharger - Brewster, NY

    I stopped by today to see how work was progressing. Site preparation work underway with tree work in progress. Stump grinding appears to be in marked path to power access point. I live nearby and pass by almost every day. I will post update with pictures as work progresses. When I can say...