Station looks ready. Not sure if there's a transformer yet though. There is one about 100-200 feet away but I can't tell if it's for the Superchargers or the nearby building.
Stopped past today. Cabinets are on site (can't tell if they're installed as the site is fenced off with a cover). Pedestal bases are in but the pedestals are not.
The superchargers I've seen with handicapped spots seem to have different signage than normal handicapped parking spots. They say "Designed for disabled access Use Last" Compared to normal handicap spots that typically say something like: "Reserved parking, minimum fine $xxx) So I doubt one...
Visited today (2/4) and there was work equipment on site but nobody working (it's a weekend). Interestingly 8 stalls are uncovered and the others are all covered.
It seems the building permit applied for on 1/13/23 was voided, and a new one was submitted. Application review is scheduled for 2/8/23.
New Permit - Bouldercolorado.gov
Interestingly the valuation of the site went from $120,000 to ~$16,000
This site has moved from Administrative Review to Building Permit. It seems the building permit was submitted on 1/11/23
https://bouldercolorado.gov/development-review-cases-map