evgo is installing superchargers in the parking lot, and i talked to the guy in charge of installing them.
he told me pge is minimum 1 year out for a transformer on the project, so these evgo chargers wont be open till minimum q3 2024, and the companies building transformers for electrical companies building out car chargers have a minimum 1 year build time.
the evgo chargers are technically a different address than the tesla chargers, the chargers are basically in the same parking lot though.
assuming the wait from pge is the same deal with tesla, these 32 stalls wont be available for use until q3 2024 also.
the guys told me when they are done with their evgo project here in livermore they will be headed to yosemite valley and installing 56 rivian chargers, and when the snow melts on tioga pass, in tuolumne meadows they have another 4 rivian chargers to install.
they also mentioned they are installing rivian chargers in 44 different national and state parks in nevada, however i dont know much about nevada and will be google searching to find out if there really is 44 parks in nevada