Circling back to the August posts from
@charlesj and
@scotsmanswan talking about site visits.
I wonder if either of you (or anyone else) that was in the system in that timeframe has actually seen their project progress. I had my site visits (Chicago suburbs) in August as well and almost immediately had the permits pulled and approved (August 30).
Then...the familiar Tesla tumbleweeds and silence. I poke them every now and then, but the answer is never specific to me, just "Ready to schedule you in the next couple of weeks" and then they ghost me again. I'm used to it...they did the same with the original installation.
I'm just wondering if anyone has a full timeline on an additional powerwall installation that Tesla might have completed recently. If you had a second or third wall added to an existing system and they came in October/November....when did you place the original order? What did your timeline look like?