I read a number of threads discussing the painfully long wait to have Powerwalls installed for your home.
I thought I'd share my timeline because the install was just recently completed.
I had four (4) Powerwalls installed.
Prior to initiating the powerwall adventure I already had a 13.8 kW PV system in place and a backup generator.
I used a solar company who carries powerwalls in stock and services Kentucky, Ohio, and Indiana
Timeline:
07/17/19 - Initial phone contact w/sales
07/12/19 - Initial "dirty" quotes for a 2, 3, and 4 powerwall install
07/17/19 - Conference call with techs and installers for Q & A
07/26/19 - First real proposal
07/30/19 - Second proposal w/ amendments
08/13/19 - Sales Contract
08/14/19 - Signed contract and down payment made
08/25/19 - Final pre-install site visit
09/23/19 - Installation begins
09/25/19 - Installation complete
10/01/19 - County Inspection
Two and a half months cradle to grave.
It would have been quicker but I asked hundreds of questions
I thought I'd share my timeline because the install was just recently completed.
I had four (4) Powerwalls installed.
Prior to initiating the powerwall adventure I already had a 13.8 kW PV system in place and a backup generator.
I used a solar company who carries powerwalls in stock and services Kentucky, Ohio, and Indiana
Timeline:
07/17/19 - Initial phone contact w/sales
07/12/19 - Initial "dirty" quotes for a 2, 3, and 4 powerwall install
07/17/19 - Conference call with techs and installers for Q & A
07/26/19 - First real proposal
07/30/19 - Second proposal w/ amendments
08/13/19 - Sales Contract
08/14/19 - Signed contract and down payment made
08/25/19 - Final pre-install site visit
09/23/19 - Installation begins
09/25/19 - Installation complete
10/01/19 - County Inspection
Two and a half months cradle to grave.
It would have been quicker but I asked hundreds of questions