I have a second Tesla solar install scheduled next week. I recently became dissatisfied with the proposed PW layout. I'm trying to better understand my options to relocated / consolidate equipment or scale back the project. Here are some questions I have right now...
Background - Located in Kailua, HI
Existing system - 42 panels (~17 KW), 2 PW 2, 18 months old, picture below
Proposed addition - 12 panels (~4.4 KW), 4 PW 2+ (I think this is what is spec'd but not sure its guaranteed?)
The 4 PW are going to be a bit "scattered" along various parts of my house. Apparently installation parameters have become far more restrictive since my last install.
1. How difficult would it be to add some of these PW later myself? I have read briefly and it doesn't seem too cosmic. For example, could I go from 2-4 or 4-6 without pulling an additional permit?
2. Do the following install restrictions sound correct?
- A PW cannot be installed above another PW
- A PW must be seperated from an adjacent PW by at least 3 ft.
(My existing system has two PW side by side. I assumed we could stack at least 1 PW, maybe 2. I'm told they are too close together to meet newer install restrictions.)
Background - Located in Kailua, HI
Existing system - 42 panels (~17 KW), 2 PW 2, 18 months old, picture below
Proposed addition - 12 panels (~4.4 KW), 4 PW 2+ (I think this is what is spec'd but not sure its guaranteed?)
The 4 PW are going to be a bit "scattered" along various parts of my house. Apparently installation parameters have become far more restrictive since my last install.
1. How difficult would it be to add some of these PW later myself? I have read briefly and it doesn't seem too cosmic. For example, could I go from 2-4 or 4-6 without pulling an additional permit?
2. Do the following install restrictions sound correct?
- A PW cannot be installed above another PW
- A PW must be seperated from an adjacent PW by at least 3 ft.
(My existing system has two PW side by side. I assumed we could stack at least 1 PW, maybe 2. I'm told they are too close together to meet newer install restrictions.)