Hi TMC Folks,
Been lurking here for about 3 months and learning what I can from the experiences and expertise in this forum. I'm finally at the stage in my solar roof order where I've gotten a site plan and now I have some questions that I hope some of you can answer.
The current plan has ~145 modules or ~8.5kW divided into three planes North, East , South. I'm in the USA (~45.512 N latitude). So obviously the south plane will get generate the most power per module (ignoring shading due to trees and other obstructions).
The original design had ~3kW on the south, 4kW on the North and 1.5KW on the east. The east is also heavily shaded by trees. North and south have minimal (basically none on south) shading due to trees. This was already less than ideal. The layout seemed to have space for another 10 or so modules on the south side. I asked them several times to change the layout and they kept saying "design changes are impossible at this point".
They never showed me any schematics or design proposals other than the layout up till that point.
Then I got the site plan and things got even worse....
They selected a single inverter with 3 MPPT ports. With a maximum of two strings per port and 35 modules per string. This made it basically impossible to isolate all the planes. But worse they decided to not isolate the south plane at all. And even more worse they cut the south size by 50% and moved it to the north (so much for design changes being impossible).
This is all pretty disheartening and I'm on the verge of cancelling my order.
My questions or I guess more a plea for advise are:
A) Is the design changes in the site plan as bad as I think they are? Connecting a north and south string and a north and east string together must cause a major drop in efficiency of the array.
B) How would you approach Tesla to try and get more modules moved to the south side? Everything I've tried up till this point has failed.
Even before the design change it looked like there was room for another 10 modules on the south side. It seems like they could either reduce the total number of active modules, fully populate AND isolate the south string(s) and still produce the same amount of energy. OR produce more energy by fully populating AND isolating the south string(s) but keep the same number of modules.
Thanks!
Solar Roof 2020 (maybe?)
Been lurking here for about 3 months and learning what I can from the experiences and expertise in this forum. I'm finally at the stage in my solar roof order where I've gotten a site plan and now I have some questions that I hope some of you can answer.
The current plan has ~145 modules or ~8.5kW divided into three planes North, East , South. I'm in the USA (~45.512 N latitude). So obviously the south plane will get generate the most power per module (ignoring shading due to trees and other obstructions).
The original design had ~3kW on the south, 4kW on the North and 1.5KW on the east. The east is also heavily shaded by trees. North and south have minimal (basically none on south) shading due to trees. This was already less than ideal. The layout seemed to have space for another 10 or so modules on the south side. I asked them several times to change the layout and they kept saying "design changes are impossible at this point".
They never showed me any schematics or design proposals other than the layout up till that point.
Then I got the site plan and things got even worse....
They selected a single inverter with 3 MPPT ports. With a maximum of two strings per port and 35 modules per string. This made it basically impossible to isolate all the planes. But worse they decided to not isolate the south plane at all. And even more worse they cut the south size by 50% and moved it to the north (so much for design changes being impossible).
This is all pretty disheartening and I'm on the verge of cancelling my order.
My questions or I guess more a plea for advise are:
A) Is the design changes in the site plan as bad as I think they are? Connecting a north and south string and a north and east string together must cause a major drop in efficiency of the array.
B) How would you approach Tesla to try and get more modules moved to the south side? Everything I've tried up till this point has failed.
Even before the design change it looked like there was room for another 10 modules on the south side. It seems like they could either reduce the total number of active modules, fully populate AND isolate the south string(s) and still produce the same amount of energy. OR produce more energy by fully populating AND isolating the south string(s) but keep the same number of modules.
Thanks!
Solar Roof 2020 (maybe?)