03/28/19 - Filled out Request for Information on Tesla website
04/03/19 - Created EnergySage account, most quote were Panasonic panel at $2.80ish
04/05/19 - Missed call back from Energy team, called and was sent a link to fill out basic information. Solar reservation made
04/06/19 - Scheduled Home Assessment on 04/12/19
04/12/19 - Site assessment
04/13/19 - Contacted by Energy Advisor for more detailed information (usage, panel option, powerwall)
4/13~4/19 - Back and forth communication on design, Q&A etcs
04/19/19 - First design complete, system too small for my liking, Tesla was using last 12 months of usage. Talked to the advisor and he will make the system bigger. Panasonic + Delta Inverter and $3.49/W
04/23/19 - Second design, almost there but want 2 more panels to get to 9kW. Panasonic + SolarEdge and $2.85/W.
04/26/19 - Talked to the Energy Advisor. Third design, 9.24kW but want to move PowerWall/Gateway/Load Center to exterior wall and asked about PowerWall reservation pricing
05/04/19 - Fourth design with exterior install
05/07/19 - Signed contract and bunch of documents as they appears in the Tesla account, contacted by Energy Project Coordinator
05/09/19 - Contacted by Re-roofing team and roofer to discuss any additional works (replacing skylights and adding vents)
05/13/19 - Contacted by Re-roofing team that roofer can start on 5/20/19, but skylights won't arrive until 5/22. Roofer will start on 6/3/19
05/21/19 - Roofer can start on 5/28, works for me.
05/22/19 - Roofer can actually starts 5/23 but since I already requested 5/28 off, sticking with that day.
05/23/19 - Energy Project Coordinator texted permit is due on 5/30 for solar install.
05/28/19 - Roofer showed up and started re-roofing
04/03/19 - Created EnergySage account, most quote were Panasonic panel at $2.80ish
04/05/19 - Missed call back from Energy team, called and was sent a link to fill out basic information. Solar reservation made
04/06/19 - Scheduled Home Assessment on 04/12/19
04/12/19 - Site assessment
04/13/19 - Contacted by Energy Advisor for more detailed information (usage, panel option, powerwall)
4/13~4/19 - Back and forth communication on design, Q&A etcs
04/19/19 - First design complete, system too small for my liking, Tesla was using last 12 months of usage. Talked to the advisor and he will make the system bigger. Panasonic + Delta Inverter and $3.49/W
04/23/19 - Second design, almost there but want 2 more panels to get to 9kW. Panasonic + SolarEdge and $2.85/W.
04/26/19 - Talked to the Energy Advisor. Third design, 9.24kW but want to move PowerWall/Gateway/Load Center to exterior wall and asked about PowerWall reservation pricing
05/04/19 - Fourth design with exterior install
05/07/19 - Signed contract and bunch of documents as they appears in the Tesla account, contacted by Energy Project Coordinator
05/09/19 - Contacted by Re-roofing team and roofer to discuss any additional works (replacing skylights and adding vents)
05/13/19 - Contacted by Re-roofing team that roofer can start on 5/20/19, but skylights won't arrive until 5/22. Roofer will start on 6/3/19
05/21/19 - Roofer can start on 5/28, works for me.
05/22/19 - Roofer can actually starts 5/23 but since I already requested 5/28 off, sticking with that day.
05/23/19 - Energy Project Coordinator texted permit is due on 5/30 for solar install.
05/28/19 - Roofer showed up and started re-roofing