So, made some progress. Since my last update:
- All charge controller wiring is done
- Output DC wiring to load centers
- Input DC PV wiring to a junction box for connection in the near future
- Low voltage communication wiring all done
- Ethernet for each of the 17 charge controllers
- Two RJ11 connections per charge controller to daisy chain them for syncing
- All inverter low voltage communication/sync wiring complete (Outback HUB10)
- All AC output wiring from the inverters to the distribution block and transfer switches is complete (pic earlier in the thread)
- All AC input wiring to the inverters from the grid are complete
- For charging the batteries off of the grid when insufficient solar is available (should be less than 1% of the time)
- No feeding *into* the grid here (for now anyway, we'll see how much excess I end up with in the summer)
- All inverter load centers ready for DC wiring to the battery bank
- Installed dedicated ethernet switch for the charge controllers and inverter controller for monitoring and easily tying to my network
- Crimped ~50 RJ45 CAT6 ends and ~35 RJ11 ends (hands are sore...)
Still some things to do before I get to the batteries.
Tonight I'm going to install the covers on all of the charge controllers temporarily (will need to remove for inspection probably in a few weeks when everything is done for phase 2) and wire all of the DC +/- bus bars in the load centers to a heavy duty 48V power supply (not isolated, so fed by a small generator).
I plan to fire up each inverter and test functionality individually. Then I will sync them all with their HUB and make sure all of the AC output wiring syncs up properly. I'll then test that AC input pass through syncs up. Hopefully all goes well. I *think* the inverters need a firmware update, but I'm not going to do that while running from a power supply. They won't sync if they are on differing firmwares, so I may hook up a pair of mostly-charged battery modules to power them one at a time and do updates if needed. I don't trust the power supply and generator to not fail during the update process and end up bricking my inverters...
Assuming the inverters check out, I'll start powering on charge controllers without PV input. This should let me configure them all, test that they're connected properly with their LV daisy chain, give them IPs on my network, etc.
When that all goes well, I'll start installation of the large + and - battery bank copper bus bars and completing the inverter load center side of that wiring. Then, I'll run another test, this time feeding the bus bars with my power supply.
After everything checks out it'll finally be time to start installing the battery bank.
------
Wired charge controllers without covers.
Charge controllers and some inverters.
Inverters!
Outback HUB10 (inverter sync)
Cheap ethernet switch for all of this equipment.