We've been waiting for our install since ordering in the Jan/Feb timeframe. We were suppose to have our solar installed the last week of March with PWs in the fall when they had teams available and could schedule. Also turned out we needed a main panel upgrade and since Tesla was booked out for months were were told for that work we opted to hire our own electrician to do the work. He got the permit, and the day he was to start in March, our county shut down and our city building department along with it, not permitting the work. End of March while waiting we decided to upgrade our system from 2PWs to 3. Our city was still WFH but at that point was processing permits but we were told weeks behind with all the contractors' request and things were moving very slowly. In mid-May we got the main panel work finalized when the inspectors were able to go out to the field for these type of "non-essential" home projects. Coming back to our additional PW, our city made our TE team file a separate permit for the additional PW so more time and cost to TE involved. This was early June and that got approved mid-June.
When TE lowered prices on our solar panels in June we called them on 6/25 to get a status on our project and hoping for some update on a scheduled date. We also inquired about the GW2 which we had told TE back in Jan/Feb if it was available come install time that we wanted the newer equipment (was going inside our garage next to the PWs). They said they were updating the accounts and there was a note on our account that GW2 was to be installed. We spoke with them again like a week later when we received our Engineering plans filed with the city and noticed it still referred to GW1. We questioned if the city would have a problem with a GW2 being installed if GW1 was on the plans. We were told an update had been filed with the city on the 26th and they were awaiting the permit now from the city before they could schedule installation.
All I can say is it has been a long process and covid and our city (who supposedly has been very proactive in getting solar installs approved and finalized) has been our stumbling block on a number of occasions. If it takes our city 2 weeks or more to get the approved permit to TE then we should be coming up on scheduiling soon. It is what it is I guess. Covid has taught patience. From TE's end we've been told we are essentially ready to go except now for the permit in their hands and a date. I'm just hoping our county doesn't close this type of work again due to covid statistics. Good luck OP on yours.