JeremyWhaling
Member
Ordered June 8
Initial design ready for review June 11
Site inspection June 13
Roof vents moved to make way for solar June 24
New design ready for review July 2
Installation July 20
First inspection with city (failed) July 30
Second inspection with city (passed) August 6
Now waiting on interconnection agreement to be sent to SCE (already reached out to the NEM folks at SCE, nothing submitted as of 8/10, but did call Tesla after leaning of this and the documents should be submitted within a few days)
Small system, LA area.
Initial design ready for review June 11
Site inspection June 13
Roof vents moved to make way for solar June 24
New design ready for review July 2
Installation July 20
First inspection with city (failed) July 30
Second inspection with city (passed) August 6
Now waiting on interconnection agreement to be sent to SCE (already reached out to the NEM folks at SCE, nothing submitted as of 8/10, but did call Tesla after leaning of this and the documents should be submitted within a few days)
Small system, LA area.